Exam 9: Estimating and Managing Costs
Exam 1: Introduction to Project Management86 Questions
Exam 2: Project Profiling68 Questions
Exam 3: Project Phases and Organization80 Questions
Exam 4: Understanding and Meeting Client Expectations59 Questions
Exam 5: Working With People on Projects71 Questions
Exam 6: Communication Technologies71 Questions
Exam 7: Starting a Project74 Questions
Exam 8: Project Time Management73 Questions
Exam 9: Estimating and Managing Costs65 Questions
Exam 10: Managing Project Quality70 Questions
Exam 11: Managing Project Risk65 Questions
Exam 12: Project Procurement and Closure70 Questions
Select questions type
The RFP is sent to a list of vendors who are _____ -meet standards of reliability and capability-to perform the required work.
(Short Answer)
4.8/5
(39)
It is possible to calculate how much money needs to be spent by any particular date during a project.
(True/False)
4.7/5
(34)
A budget estimate based on a similar project is an) _____ estimate.
(Multiple Choice)
4.7/5
(35)
_____ is the revised project budget based on actual cost to date plus the estimate to complete.
(Multiple Choice)
4.8/5
(39)
_____ is the estimate of the amount of money needed to fill the unfinished part of the project.
(Multiple Choice)
4.9/5
(34)
Which of the following indicates that a project is behind schedule?
(Multiple Choice)
4.8/5
(33)
_____ is the detailed cost estimates for each activity in the project.
(Multiple Choice)
4.9/5
(36)
_____ is a method of comparing the budgeted and actual costs of a project periodically during the project.
(Multiple Choice)
4.9/5
(27)
The process of subtotaling costs by category is called reconciliation.
(True/False)
4.9/5
(39)
_____ refers) to decisions based on incomplete information made by people who have extensive personal experience.
(Multiple Choice)
4.8/5
(44)
The schedule variance and the cost variance provide the amount by which the spending is behind or ahead of) schedule and the amount by which a project is exceeding or less than) its budget.
(True/False)
4.9/5
(41)
_____ is the sum of the items in the budgeted cost of work scheduled that should have been spent by a particular day.
(Multiple Choice)
4.9/5
(38)
The ratio of the earned value to the planned value is the _____.
(Short Answer)
4.8/5
(37)
If the costs of the activities up to the present vary from the original estimates, it will affect the total estimate for the project cost.
(True/False)
4.8/5
(40)
Showing 41 - 60 of 65
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)