Exam 9: Estimating and Managing Costs
Exam 1: Introduction to Project Management86 Questions
Exam 2: Project Profiling68 Questions
Exam 3: Project Phases and Organization80 Questions
Exam 4: Understanding and Meeting Client Expectations59 Questions
Exam 5: Working With People on Projects71 Questions
Exam 6: Communication Technologies71 Questions
Exam 7: Starting a Project74 Questions
Exam 8: Project Time Management73 Questions
Exam 9: Estimating and Managing Costs65 Questions
Exam 10: Managing Project Quality70 Questions
Exam 11: Managing Project Risk65 Questions
Exam 12: Project Procurement and Closure70 Questions
Select questions type
The schedule variance is the difference between the earned value and the planned value.
(True/False)
4.8/5
(41)
If a project consists of activities that are common to many other projects, _____ are available per unit.
(Multiple Choice)
4.9/5
(30)
At the end of three months, the cost factors in A&B's healthcare project are as follows: Earned value = $17,000, Actual cost = $18,200. What is the cost variance CV) and cost performance index CPI) for the project?
(Multiple Choice)
4.7/5
(34)
Which of the following is true about management reserves versus contingency reserves?
(Multiple Choice)
5.0/5
(41)
Estimates that are calculated by multiplying measured parameters by cost-per-unit values are _____ estimates.
(Short Answer)
4.9/5
(39)
The project manager prefers to keep the company's money working in other investments until the last moment before transferring it to the project account.
(True/False)
4.8/5
(41)
In estimating costs to compare and select projects, which of the following is true
(Multiple Choice)
4.9/5
(45)
To calculate the ETC, the manager must decide if the schedule variance observed in the estimates to that point are representative of the future.
(True/False)
4.9/5
(33)
If services or products will be provided by vendors, the cost of those services can be determined by issuing an RFP.
(True/False)
4.9/5
(27)
To calculate the EAC, the estimate to complete ETC) is added to the actual cost AC) of the activities already performed.
(True/False)
4.8/5
(42)
_____ are measurable factors that can be used in an equation to calculate a result.
(Multiple Choice)
4.9/5
(37)
If the cost estimates by vendors are much higher than expected and if the project cannot be completed for the cost that was used to select the project, the selection decision might have to be reconsidered.
(True/False)
4.9/5
(41)
Jean is managing a project in his organization. The planned value for this project is $4,500. At the end of eight weeks, he finds that his earned value is $3,500. What is the present schedule variance for the project? What does the variance signify?
(Multiple Choice)
4.9/5
(44)
Contractual agreements with vendors always require full payment of their costs during the project.
(True/False)
4.9/5
(32)
Earned value management allows for partial completion of an activity if some of the detailed costs associated with the activity have been paid but others have not.
(True/False)
4.9/5
(30)
Estimates in the earliest stages of project selection are usually made using estimates based from previous projects that can be _____-multiplied by an adjustment factor to make the new estimate proportional to the original.
(Multiple Choice)
4.8/5
(35)
The difference between the earned value and the actual cost is the cost performance index.
(True/False)
4.7/5
(43)
During the project, the manager can evaluate the _____ using the cost variance CV) and the cost performance index CPI).
(Short Answer)
4.8/5
(44)
Showing 21 - 40 of 65
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)