Exam 26: Learning Curves
Exam 1: Operations and Productivity126 Questions
Exam 2: Operations Strategy in a Global Environment119 Questions
Exam 3: Project Management120 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services118 Questions
Exam 6: Managing Quality123 Questions
Exam 7: Process Strategy108 Questions
Exam 8: Capacity and Constraint Management96 Questions
Exam 9: Location Strategies120 Questions
Exam 10: Layout Strategies146 Questions
Exam 11: Human Resources, job Design, and Work Measurement154 Questions
Exam 12: Supply Chain Management144 Questions
Exam 13: Inventory Management163 Questions
Exam 14: Aggregate Planning and Sop116 Questions
Exam 15: Material Requirements Planning Mrpand Erp113 Questions
Exam 16: Short-Term Scheduling116 Questions
Exam 17: Jit, tps, and Lean Operations115 Questions
Exam 18: Maintenance and Reliability111 Questions
Exam 19: Sustainability in the Supply Chain80 Questions
Exam 20: Statistical Process Control144 Questions
Exam 21: Supply Chain Management Analytics55 Questions
Exam 22: Decision-Making Tools97 Questions
Exam 23: Linear Programming80 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves105 Questions
Exam 27: Simulation75 Questions
Select questions type
Which of the following statements comparing learning curve rates (L)to improvement rates is TRUE?
(Multiple Choice)
4.9/5
(34)
If the first unit in a series of units takes 200 days to complete,and the learning curve is 80%,then the second unit will take 160 days.
(True/False)
4.8/5
(48)
________ are based on the premise that people and organizations get better at their tasks as the tasks are repeated.
(Short Answer)
4.7/5
(36)
The first unit took 10 hours and the third unit took 5.68 hours.What is the improvement rate?
(Multiple Choice)
4.7/5
(39)
A company negotiates a price for two aircraft that includes a reduction in labor on the second aircraft consistent with a 70% learning curve.Suppose the first aircraft took 100 hours.If the improvement rate changes to 20%,how will the total time to complete both aircraft change?
(Multiple Choice)
4.9/5
(32)
Sally suspects strongly that there is a learning curve associated with solving problems assigned for operations management.She notes that it took her approximately 33 minutes to solve the first problem and 20 minutes to solve the fifth problem.
a.Estimate Sally's learning curve.
b.Using your answer from part a,estimate how much longer it will take Sally to finish the three problems that remain.
(Essay)
4.7/5
(33)
Which one of the following statements about learning curves is TRUE?
(Multiple Choice)
4.9/5
(34)
Describe the earliest application of learning curve concepts to industry.
(Short Answer)
4.8/5
(33)
The doubling approach to learning curve calculations allows us to determine the hours required for any unit.
(True/False)
4.8/5
(31)
Explain how learning curves might be applied in a scheduling application.
(Essay)
4.9/5
(31)
In the formula approach to learning curve calculations,you have used the formula TN = T1 (Nb).Your manager shows you a problem for which b is specified as -.18443.What learning curve does that value represent?
(Essay)
4.8/5
(41)
Learning curves can be applied to a variety of purposes internal to a firm,including:
(Multiple Choice)
5.0/5
(34)
The earliest application of learning curves appears in the work of architect Frank Lloyd Wright.
(True/False)
4.9/5
(35)
Your firm has expertise with a special type of hand-finished furniture.The learning curve is known to be 82%.If the first piece of furniture took 6 hours,estimate (using the doubling approach)how long it will take to complete the third unit.
(Essay)
4.8/5
(34)
The ________ is the simplest approach to learning curve problems.
(Short Answer)
4.8/5
(26)
The first unit of a product took 80 work days.The learning curve is estimated to be 90%.The time for the fourth unit will be about ________ work days and the time for the first four units will be about ________ work days.(Use Table E.3)
(Multiple Choice)
4.8/5
(27)
The first unit of a product took 50 hours to build,and the learning curve is 80%.How long will it take to make the third unit? (Use at least three decimals in the exponent if you use the formula approach.)
(Multiple Choice)
4.8/5
(31)
The Learning-Curve Coefficients table reports that for 70 percent learning,the eighth unit has a unit time value of 0.343.Verify that table entry by use of the doubling method.
(Essay)
4.8/5
(40)