Exam 14: Material Requirements Planning Mrpand Erp
Exam 1: Operations and Productivity127 Questions
Exam 2: The Global Environment and Operations Strategy119 Questions
Exam 3: Managing Projects120 Questions
Exam 4: Forecasting Demand140 Questions
Exam 5: Product Design118 Questions
Exam 6: Quality Management and International Standards123 Questions
Exam 7: Process Design108 Questions
Exam 8: Location Decisions121 Questions
Exam 9: Layout Decisions146 Questions
Exam 10: Job Design and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Managing Inventory163 Questions
Exam 13: Aggregate Scheduling116 Questions
Exam 14: Material Requirements Planning Mrpand Erp113 Questions
Exam 15: Scheduling for the Short-Term116 Questions
Exam 16: Jit,lean Operations,and the Toyota Production System115 Questions
Exam 17: Maintenance and Reliability Decisions111 Questions
Exam 18: Sustainability80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity Planning96 Questions
Exam 21: Supply Chain Modeling55 Questions
Exam 22: Decision Modeling97 Questions
Exam 23: Linear Programming Models88 Questions
Exam 24: Transportation Modeling89 Questions
Exam 25: Queuing Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Modeling with Simulation75 Questions
Select questions type
Consider the following product structure.Fifty units of Product A are needed.How many units of B,C,D,and E are needed? 

Free
(Essay)
4.8/5
(36)
Correct Answer:
Item B: 50(2)= 100 units;Item C: 50( 3)= 150 units;Item D: 50(2)(1)+ 50(3)(1)= 250 units;Item E: 50(3)(2)= 300 units
Bills of material organized by major subassemblies or by product options are called ________.
Free
(Essay)
4.9/5
(41)
Correct Answer:
modular bills
Which of the following is NOT one of the four key tasks that Wheeled Coach insists are necessary for successful MRP implementation?
Free
(Multiple Choice)
4.9/5
(40)
Correct Answer:
E
DRP is a time-phased stock-replenishment plan for all levels of a distribution network.
(True/False)
4.9/5
(41)
Consider the following product structure.
If the demand for product A is 30 units,and there are 10 units of B on hand and none of C,how many units of part D will be needed?

(Multiple Choice)
4.8/5
(30)
If the explosion of the bill of material tells MRP how much of each part is needed,how does MRP learn when each of these parts is needed?
(Essay)
4.8/5
(34)
Product A is made from 2 Bs and 1 C.Lead times for A,B,and C are 2,3,and 2 weeks respectively.Currently there are 2 Bs and a 5 Cs on hand,with 5 of each scheduled to arrive at the end of week 1.If 20 As are needed during week 4,can the order be completed (it is the start of week 0 currently)?
(Essay)
4.7/5
(38)
Effective use of MRP and other dependent demand models does not require which of the following?
(Multiple Choice)
5.0/5
(34)
Which of the following is FALSE concerning enterprise resource planning (ERP)?
(Multiple Choice)
4.8/5
(29)
An order for 110 units of Product A has been placed.There are currently 60 units of Product A on hand.Each A requires 4 units of Part B.There are 20 units of B available.What are the net requirements for B?
(Multiple Choice)
4.9/5
(36)
A(n)________ is a bill of material for components,usually subassemblies,that exist only temporarily;they are never inventoried.
(Essay)
4.9/5
(24)
The time-phased product structure,unlike the bill of material,adds the concept of lead times.
(True/False)
4.8/5
(30)
The quantity required of a dependent demand item is computed from the demand for the final products in which the item is used.
(True/False)
4.8/5
(29)
Which of the following lot-sizing techniques results in the lowest holding costs?
(Multiple Choice)
4.8/5
(43)
What lot-sizing technique is generally preferred when inventory holding costs are extremely high?
(Multiple Choice)
4.9/5
(32)
Which of the following statements best compares modular bills and phantom bills?
(Multiple Choice)
4.8/5
(39)
Construct a product structure tree for a movie purchased in DVD format.Assume that it contains a single DVD disk.Don't be concerned with artwork-you may use labeled boxes for your parts and assemblies.
(Essay)
4.9/5
(31)
When safety stock is deemed absolutely necessary,the usual policy is to build it into (increase)the inventory requirement of the MRP logic.