Exam 14: Material Requirements Planning Mrpand Erp

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

Consider the following product structure.Fifty units of Product A are needed.How many units of B,C,D,and E are needed? Consider the following product structure.Fifty units of Product A are needed.How many units of B,C,D,and E are needed?

Free
(Essay)
4.8/5
(36)
Correct Answer:
Verified

Item B: 50(2)= 100 units;Item C: 50( 3)= 150 units;Item D: 50(2)(1)+ 50(3)(1)= 250 units;Item E: 50(3)(2)= 300 units

Bills of material organized by major subassemblies or by product options are called ________.

Free
(Essay)
4.9/5
(41)
Correct Answer:
Verified

modular bills

Which of the following is NOT one of the four key tasks that Wheeled Coach insists are necessary for successful MRP implementation?

Free
(Multiple Choice)
4.9/5
(40)
Correct Answer:
Verified

E

DRP is a time-phased stock-replenishment plan for all levels of a distribution network.

(True/False)
4.9/5
(41)

Consider the following product structure. Consider the following product structure.   If the demand for product A is 30 units,and there are 10 units of B on hand and none of C,how many units of part D will be needed? If the demand for product A is 30 units,and there are 10 units of B on hand and none of C,how many units of part D will be needed?

(Multiple Choice)
4.8/5
(30)

If the explosion of the bill of material tells MRP how much of each part is needed,how does MRP learn when each of these parts is needed?

(Essay)
4.8/5
(34)

Product A is made from 2 Bs and 1 C.Lead times for A,B,and C are 2,3,and 2 weeks respectively.Currently there are 2 Bs and a 5 Cs on hand,with 5 of each scheduled to arrive at the end of week 1.If 20 As are needed during week 4,can the order be completed (it is the start of week 0 currently)?

(Essay)
4.7/5
(38)

Distribution resource planning (DRP)is:

(Multiple Choice)
4.8/5
(39)

Effective use of MRP and other dependent demand models does not require which of the following?

(Multiple Choice)
5.0/5
(34)

MRP II is accurately described as:

(Multiple Choice)
4.8/5
(29)

Which of the following is FALSE concerning enterprise resource planning (ERP)?

(Multiple Choice)
4.8/5
(29)

An order for 110 units of Product A has been placed.There are currently 60 units of Product A on hand.Each A requires 4 units of Part B.There are 20 units of B available.What are the net requirements for B?

(Multiple Choice)
4.9/5
(36)

A(n)________ is a bill of material for components,usually subassemblies,that exist only temporarily;they are never inventoried.

(Essay)
4.9/5
(24)

The time-phased product structure,unlike the bill of material,adds the concept of lead times.

(True/False)
4.8/5
(30)

The quantity required of a dependent demand item is computed from the demand for the final products in which the item is used.

(True/False)
4.8/5
(29)

Which of the following lot-sizing techniques results in the lowest holding costs?

(Multiple Choice)
4.8/5
(43)

What lot-sizing technique is generally preferred when inventory holding costs are extremely high?

(Multiple Choice)
4.9/5
(32)

Which of the following statements best compares modular bills and phantom bills?

(Multiple Choice)
4.8/5
(39)

Construct a product structure tree for a movie purchased in DVD format.Assume that it contains a single DVD disk.Don't be concerned with artwork-you may use labeled boxes for your parts and assemblies.

(Essay)
4.9/5
(31)

When safety stock is deemed absolutely necessary,the usual policy is to build it into (increase)the inventory requirement of the MRP logic.

(True/False)
4.7/5
(31)