The first unit of a product took 80 work days.The learning curve is estimated to be 90%.The time for the fourth unit will be about ________ work days and the time for the first four units will be about ________ work days.(Use Table E.3)

Free
(Multiple Choice)
4.9/5
(41)
Correct Answer:
Verified

C

When comparing a 70% learning curve versus a 90% learning curve,which one results in a more rapid reduction in labor requirements? Why?

Free
(Essay)
5.0/5
(33)
Correct Answer:
Verified

Learning curves are defined in terms of the complements of their improvement rates.A 70% learning curve implies a 30% decrease in time each time the number of replications is doubled.A 90% learning curve implies a 10% decrease in time each time the number of replications is doubled.Therefore,the reduction in labor requirements is more rapid at 70% than at 90%.

The earliest application of learning curves appears in the work of architect Frank Lloyd Wright.

Free
(True/False)
4.9/5
(33)
Correct Answer:
Verified

False

A job with a 90% learning curve required 20 hours for the initial unit.The fourth unit should require approximately how many hours?

(Multiple Choice)
4.9/5
(39)

________ are based on the premise that people and organizations get better at their tasks as the tasks are repeated.

(Essay)
4.9/5
(28)

Joe's Manufacturing is considering bidding on a small order for 5 units.Based on similar products that they have made in the past,they believe that the first unit will take 500 labor hours.They also believe that there will be an 80% learning curve.How many hours of labor should Joe include for his bid?

(Essay)
4.9/5
(41)

In the formula to compute the time for the Nth unit,TN = T1(Nb),the exponent b is the learning curve rate L,expressed as a decimal.

(True/False)
4.9/5
(38)

A 100% learning curve implies that:

(Multiple Choice)
4.9/5
(34)

The learning curve in the steel industry and the learning curve in heart transplants have both been estimated at 79 percent.

(True/False)
4.8/5
(33)

Learning curves can be used to establish budgets.

(True/False)
4.7/5
(35)

When learning curves are plotted on ________ scales,the "curves" become straight lines.

(Essay)
4.7/5
(30)

The ________ is the simplest approach to learning curve problems.

(Essay)
4.9/5
(29)

The first unit took 79 hours;the tenth took 46 hours.What learning curve is implied by the data?

(Essay)
4.7/5
(40)

Learning curves have a variety of purposes.Your text places them into which three broad categories?

(Multiple Choice)
4.7/5
(38)

You are a cost accountant for a firm that specializes in "small" (under 10 billion dollars)defense contracts for specialty electronics products,such as fully portable,miniaturized CD-ROM imaging stations and global positioning transmitters/transponders.Your company is well respected in this field.One project up for competitive bids is a Field Service,Hands-Free,Individual Multi-Protocol Secure Communicator (a battlefield version of a cellular telephone,but built into each soldier's helmet,and containing necessary encryption technology).The Department of Defense wants 8 of these experimental devices to test their practicality.You have reviewed the contract specifications,and estimated that the first FSHFIMPSC should require 2350 hours,and that the product is subject to a 75% learning curve.All costs of the project (machine purchase,machine time,direct and indirect labor,and materials)have been bundled (allocated)into an hourly labor rate of $172 per hour.Determine the total project cost using the provided data.

(Essay)
4.8/5
(32)

The first unit of a product took 832 hours to build,and the learning curve is 90%.How long will it take to make the 25th unit? (Use at least three decimals in the exponent if you use the formula approach. )

(Multiple Choice)
4.8/5
(38)

A defense contractor has just started producing engines for a new government contract.The first engine took 800 hours to produce.If the learning curve is 80%,how long will it take to produce the first 20 engines?

(Multiple Choice)
4.9/5
(26)

A defense contractor has just started producing turbines for a new government contract.The first turbine took 7000 hours to produce.If the learning curve is 90%,how long will it take to produce the 10th turbine? (Use at least three decimals in the exponent if you use the formula approach. )

(Multiple Choice)
4.8/5
(38)

Which of the following statements regarding the usefulness of learning curves is FALSE?

(Multiple Choice)
4.7/5
(37)

Suppose that there are two products with the same first product time.However,product A has an improvement rate of 10% while product B has an improvement rate of 20%.How much longer will it take to make the 10th unit of product A compared to product B?

(Multiple Choice)
4.9/5
(22)
Showing 1 - 20 of 110
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)