Exam 26: Operations Scheduling
Exam 1: Using Operations to Compete107 Questions
Exam 2: Project Management151 Questions
Exam 3: Process Strategy149 Questions
Exam 4: Process Analysis192 Questions
Exam 5: Quality and Performance223 Questions
Exam 6: Capacity Planning133 Questions
Exam 7: Constraint Management160 Questions
Exam 8: Lean Systems179 Questions
Exam 9: Supply Chain Inventory Management216 Questions
Exam 10: Supply Chain Design93 Questions
Exam 11: Supply Chain Location Decisions126 Questions
Exam 12: Supply Chain Integration130 Questions
Exam 13: Supply Chain Sustainability and Humanitarian Logistics77 Questions
Exam 14: Forecasting183 Questions
Exam 15: Operations Planning and Scheduling191 Questions
Exam 16: Resource Planning149 Questions
Exam 17: Decision Making118 Questions
Exam 18: Waiting Line127 Questions
Exam 19: Special Inventory Models53 Questions
Exam 20: Linear Programming84 Questions
Exam 21: Simulation61 Questions
Exam 22: Financial Analysis60 Questions
Exam 23: Acceptance Sampling Plans88 Questions
Exam 24: Measuring Output Rates103 Questions
Exam 25: Learning Curve Analysis56 Questions
Exam 26: Operations Scheduling131 Questions
Select questions type
Table J.3
Six jobs have just arrived at workstation 017;which has been idle.All the pertinent data are given in the following table.The shop works eight hours per day.It is now time zero.
-Use the information in Table J.3.If the EDD rule is used,what is the average past due?

(Multiple Choice)
4.8/5
(30)
Table J.3
Six jobs have just arrived at workstation 017;which has been idle.All the pertinent data are given in the following table.The shop works eight hours per day.It is now time zero.
-Use the information in Table J.3.If the SPT rule is used,what is the average past due?

(Multiple Choice)
4.7/5
(35)
A job's flow time at a single workstation is defined as the:
(Multiple Choice)
4.9/5
(36)
Table J.4
Workstation 1 has five jobs waiting to be processed.It is now time 0,and times are expressed in terms of days.All pertinent data are given in the following table.
-Using the information in Table J.4 and the EDD rule,what is the average flow time (in days)?

(Multiple Choice)
4.8/5
(33)
Table J.16
Five jobs are currently waiting to be processed.Each job has to go through Machine 1 first and then Machine 2 before it is completed.The processing times (in hours)for the five jobs on each machine are:
-Use the information in Table J.16.What is the makespan through both machines if Johnson's rule is used?

(Multiple Choice)
4.9/5
(33)
Table J.12
Consider the following problems in which six jobs must each be processed on two machines starting with machine 1 and then going to machine 2.The following processing times and due dates are in hours.
-Use the information in Table J.12.What sequence would you use if you wanted to minimize the makespan of the jobs?

(Multiple Choice)
4.9/5
(34)
Table J.2
Suppose that the following six jobs must be scheduled through a car repair facility:
-Use the information in Table J.2.Which one of the following jobs will be the last one completed if sequencing is done using the FCFS rule?

(Multiple Choice)
4.8/5
(34)
Table J.15
Consider the following problem in which four jobs that arrived this morning are to be processed on two machines.They start with the cutting machine and then go to the painting machine.The following processing times are available (in hours):
-Use the information in Table J.15.If the SPT rule is used to determine the sequence at the cutting machine and the same sequence is also used at the painting machine,what is the makespan through both machines?

(Multiple Choice)
4.9/5
(32)
Table J.17
A company must take on seven new projects.Each project has a planning stage and a design stage,and the planning stage must be completed before the design stage can begin.Also,two project teams are available to work on these projects: Team 1 works only on planning stages of projects,and Team 2 works only on design stages of projects.The times to complete the project stage,in days,are shown in the following table.
-Using the information in Table J.17 and Johnson's rule,develop a schedule that minimizes makespan for these seven jobs.Assume that job C could be neatly split into two equal parts,each having half of the processing time on each machine as the full job C.Using your original sequence,but splitting job C,what is the reduction in makespan for the seven jobs?

(Multiple Choice)
4.8/5
(29)
Table J.7
The following four jobs just arrived (end of hour 0)at Workstation A.They are the only ones waiting to be processed.
-Using the information in Table J.7 and the critical ratio (CR)rule,what is the job sequence?

(Multiple Choice)
4.8/5
(46)
Table J.8
Auto Data produces custom engineering testing equipment.The following six jobs are currently in the design department.The time since each one arrived,the processing time,and the due date are shown below.All times are expressed in terms of days.Let now be the beginning of Day 1.
-Using the information in Table J.8 and the FCFS rule,what is the average days past due?

(Multiple Choice)
5.0/5
(42)
Determining a production sequence for a group of jobs in a two-station flow shop to minimize the makespan has the advantage of:
(Multiple Choice)
4.9/5
(42)
Table J.12
Consider the following problems in which six jobs must each be processed on two machines starting with machine 1 and then going to machine 2.The following processing times and due dates are in hours.
-Use the information in Table J.12.What is the minimum idle time possible on machine 2?

(Multiple Choice)
4.8/5
(33)
Describe the difference between front office and back office operations from the standpoint of scheduling customer jobs.
(Essay)
4.8/5
(27)
Johnson's rule is a procedure that minimizes makespan in scheduling a group of jobs on two workstations.
(True/False)
4.8/5
(35)
Table J.4
Workstation 1 has five jobs waiting to be processed.It is now time 0,and times are expressed in terms of days.All pertinent data are given in the following table.
-Using the information in Table J.4 and the EDD rule,what is the average days past due?

(Multiple Choice)
4.8/5
(31)
Table J.1
The framing department has six jobs waiting to be processed.It is now time zero.Times are expressed in terms of days.
-Using the information in Table J.1 and the EDD rule,what is the average flow time?

(Multiple Choice)
4.9/5
(33)
Which of the following statements on an operations schedule is best?
(Multiple Choice)
4.9/5
(35)
Table J.17
A company must take on seven new projects.Each project has a planning stage and a design stage,and the planning stage must be completed before the design stage can begin.Also,two project teams are available to work on these projects: Team 1 works only on planning stages of projects,and Team 2 works only on design stages of projects.The times to complete the project stage,in days,are shown in the following table.
-Using the information in Table J.17 and Johnson's rule,what is the makespan for these seven jobs?

(Multiple Choice)
4.7/5
(38)
Table J.10
A workstation has six jobs waiting to be processed.They arrived at the end of Day 0 and it is now the beginning of Day 1.It is now time zero.Times are expressed in terms of days.
-Using the information in Table J.10 and the earliest due date (EDD)rule,which job(s)will be completed on or before their due dates?

(Multiple Choice)
4.8/5
(28)
Showing 41 - 60 of 131
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)