Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Ethical issues that may arise in projects large and small include

Free
(Multiple Choice)
4.9/5
(34)
Correct Answer:
Verified

E

Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?

Free
(Multiple Choice)
4.9/5
(39)
Correct Answer:
Verified

D

The __________ is the computed longest time path(s) through a network.

Free
(Short Answer)
4.8/5
(30)
Correct Answer:
Verified

critical path

By their very nature, projects have a limited lifetime, and that sets project management apart from the management of more traditional activities.

(True/False)
4.8/5
(31)

The __________ distribution is used by PERT analysis to calculate expected activity times and variances.

(Multiple Choice)
4.9/5
(32)

Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _________ should be crashed first, adding _________ to project cost. Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _________ should be crashed first, adding _________ to project cost.

(Multiple Choice)
4.9/5
(34)

__________ divides a project into more and more detailed components.

(Short Answer)
4.9/5
(36)

Which of the following statements regarding PERT times is true?

(Multiple Choice)
4.8/5
(31)

Which of the following statements regarding PERT times is true?

(Multiple Choice)
4.9/5
(34)

Define slack.

(Essay)
4.9/5
(44)

The project organization works best when which of the following conditions are satisfied? I. Work can be defined with a specific goal and deadline. II. The job is typical and familiar to the existing organization. III. The work contains interrelated tasks requiring specialized skills IV. The project is temporary but unimportant to long-term organizational success V. The project cuts across organizational lines.

(Multiple Choice)
4.9/5
(32)

Given the project within the table below calculate a. The critical path b. The minimum project duration c. The amount of slack for each activity Given the project within the table below calculate a. The critical path b. The minimum project duration c. The amount of slack for each activity

(Essay)
4.7/5
(37)

The shortest of all paths through the network is the critical path.

(True/False)
4.9/5
(39)

Consider the network described in the table below. Consider the network described in the table below.    a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer than 30 time units. a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer than 30 time units.

(Essay)
4.7/5
(40)

PERT, but not CPM, has the ability to consider the precedence relationships in a project.

(True/False)
4.8/5
(30)

Which of the following statements regarding Bechtel is true?

(Multiple Choice)
4.9/5
(25)

The network analysis method that allows activity times to vary is __________.

(Essay)
4.8/5
(33)

A project organization works best for an organization when the project resides in only one of its functional areas.

(True/False)
4.8/5
(32)

A project organization that becomes permanent is often referred to as a __________.

(Multiple Choice)
4.8/5
(31)

The ES of an activity that has only one predecessor is simply the EF of that predecessor.

(True/False)
4.9/5
(36)
Showing 1 - 20 of 123
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)