Exam 3: Project Management
Exam 1: Operations and Productivity126 Questions
Exam 2: Operations Strategy in a Global Environment135 Questions
Exam 3: Project Management123 Questions
Exam 4: Forecasting142 Questions
Exam 5: Design of Goods and Services137 Questions
Exam 6: Managing Quality130 Questions
Exam 7: Process Strategy129 Questions
Exam 8: Location Strategies140 Questions
Exam 9: Layout Strategies161 Questions
Exam 10: Human Resources, Job Design, and Work Measurement191 Questions
Exam 11: Supply-Chain Management145 Questions
Exam 12: Inventory Management171 Questions
Exam 13: Aggregate Planning134 Questions
Exam 14: Material Requirements Planning Mrp and Erp172 Questions
Exam 15: Short-Term Scheduling139 Questions
Exam 16: Just-In-Time and Lean Options138 Questions
Exam 17: Maintenance and Reliability130 Questions
Exam 18: Statistical Tools for Managers97 Questions
Exam 19: Acceptance Sampling99 Questions
Exam 20: The Simplex Method of Linear Programming94 Questions
Exam 21: The Modi and Vam Methods of Solving Transportation Problems135 Questions
Exam 22: Vehicle Routing and Scheduling111 Questions
Exam 23 Managing Quality155 Questions
Exam 24: Process Strategy107 Questions
Exam 25: Supply-Chain Management73 Questions
Exam 26: Vehicle Routing and Scheduling92 Questions
Select questions type
Ethical issues that may arise in projects large and small include
Free
(Multiple Choice)
4.9/5
(34)
Correct Answer:
E
Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?
Free
(Multiple Choice)
4.9/5
(39)
Correct Answer:
D
The __________ is the computed longest time path(s) through a network.
Free
(Short Answer)
4.8/5
(30)
Correct Answer:
critical path
By their very nature, projects have a limited lifetime, and that sets project management apart from the management of more traditional activities.
(True/False)
4.8/5
(31)
The __________ distribution is used by PERT analysis to calculate expected activity times and variances.
(Multiple Choice)
4.9/5
(32)
Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _________ should be crashed first, adding _________ to project cost. 

(Multiple Choice)
4.9/5
(34)
__________ divides a project into more and more detailed components.
(Short Answer)
4.9/5
(36)
Which of the following statements regarding PERT times is true?
(Multiple Choice)
4.8/5
(31)
Which of the following statements regarding PERT times is true?
(Multiple Choice)
4.9/5
(34)
The project organization works best when which of the following conditions are satisfied? I. Work can be defined with a specific goal and deadline.
II. The job is typical and familiar to the existing organization.
III. The work contains interrelated tasks requiring specialized skills
IV. The project is temporary but unimportant to long-term organizational success
V. The project cuts across organizational lines.
(Multiple Choice)
4.9/5
(32)
Given the project within the table below calculate
a. The critical path
b. The minimum project duration
c. The amount of slack for each activity


(Essay)
4.7/5
(37)
The shortest of all paths through the network is the critical path.
(True/False)
4.9/5
(39)
Consider the network described in the table below.
a. Calculate the expected duration of each activity.
b. Calculate the expected duration and variance of the critical path.
c. Calculate the probability that the project will be completed in fewer than 30 time units.

(Essay)
4.7/5
(40)
PERT, but not CPM, has the ability to consider the precedence relationships in a project.
(True/False)
4.8/5
(30)
Which of the following statements regarding Bechtel is true?
(Multiple Choice)
4.9/5
(25)
The network analysis method that allows activity times to vary is __________.
(Essay)
4.8/5
(33)
A project organization works best for an organization when the project resides in only one of its functional areas.
(True/False)
4.8/5
(32)
A project organization that becomes permanent is often referred to as a __________.
(Multiple Choice)
4.8/5
(31)
The ES of an activity that has only one predecessor is simply the EF of that predecessor.
(True/False)
4.9/5
(36)