Exam 15: Short-Term Scheduling
Exam 1: Operations and Productivity126 Questions
Exam 2: Operations Strategy in a Global Environment135 Questions
Exam 3: Project Management123 Questions
Exam 4: Forecasting142 Questions
Exam 5: Design of Goods and Services137 Questions
Exam 6: Managing Quality130 Questions
Exam 7: Process Strategy129 Questions
Exam 8: Location Strategies140 Questions
Exam 9: Layout Strategies161 Questions
Exam 10: Human Resources, Job Design, and Work Measurement191 Questions
Exam 11: Supply-Chain Management145 Questions
Exam 12: Inventory Management171 Questions
Exam 13: Aggregate Planning134 Questions
Exam 14: Material Requirements Planning Mrp and Erp172 Questions
Exam 15: Short-Term Scheduling139 Questions
Exam 16: Just-In-Time and Lean Options138 Questions
Exam 17: Maintenance and Reliability130 Questions
Exam 18: Statistical Tools for Managers97 Questions
Exam 19: Acceptance Sampling99 Questions
Exam 20: The Simplex Method of Linear Programming94 Questions
Exam 21: The Modi and Vam Methods of Solving Transportation Problems135 Questions
Exam 22: Vehicle Routing and Scheduling111 Questions
Exam 23 Managing Quality155 Questions
Exam 24: Process Strategy107 Questions
Exam 25: Supply-Chain Management73 Questions
Exam 26: Vehicle Routing and Scheduling92 Questions
Select questions type
The priority rule that sequences jobs using the smallest ratio of due date from today to processing time is
Free
(Multiple Choice)
4.8/5
(25)
Correct Answer:
A
Bob Dresser operates a major appliance warranty service center. His operation has two check stations that are required at the end of every repair task performed by his appliance repair staff. These are the Functionality Review (FR) and the Overall Scan (OS). The FR must be performed successfully before the OS is begun. On Friday morning, six repair jobs are completed, awaiting these two inspection activities. Processing times are given in minutes.
a. What is the optimal sequence of jobs for the objective of minimizing the total flow time?
b. Show your work, and document the sequence.
c. Chart the solution to this problem.
d. What jobs are being processed at time period 90?
e. What is the total flow time of this problem?



Free
(Essay)
4.8/5
(38)
Correct Answer:
(a) The optimal sequence is F-D-B-A-C-E.
(b) Supporting work appears in the table below. (c) The schedule appears in the chart below. (d) Job A is being processed at FR (Machine 1), while Job B is being processed at OS (e) Total flow time for the schedule is 185.
(Machine 2)
Some firms have developed arrangements to literally "swap" employees with each other during their respective peak demand times.
(True/False)
4.8/5
(25)
Conventional MRP uses time buckets that do not recognize capacity limits, and in fact ignores capacity issues. A more realistic scheduling system that includes work center capacities and other resource availabilities is
(Multiple Choice)
4.9/5
(35)
In forward scheduling, jobs are scheduled as late as possible within the time allowed by the customer due dates.
(True/False)
4.8/5
(39)
Jack's Refrigeration Repair is under contract to repair, recondition, and/or refurbish commercial and industrial icemakers from restaurants, seafood processors, and similar organizations. Jack currently has five jobs to be scheduled, shown in the order in which they arrived.
a. Complete the following table. (Show your supporting calculations below).
b. Which dispatching rule has the best score for flow time?
c. Which dispatching rule has the best score for work-in-process (jobs in the system)?
d. Which dispatching rule has the best score for lateness?
e. What dispatching rule would you select? Support your decision.



(Essay)
4.7/5
(31)
A Gantt load chart shows the loading and idle time of several departments, machines, or facilities.
(True/False)
4.9/5
(23)
What are the options available to operations personnel to manage facility work flow?
(Essay)
4.8/5
(32)
Short-term scheduling is important to efficiency and to cost reduction, but its impact is not of strategic importance.
(True/False)
4.7/5
(35)
Which of the following dispatching rules ordinarily gives the best results when the criterion is lowest time for completion of the full sequence of jobs?
(Multiple Choice)
4.7/5
(38)
A recent advance in short-term scheduling that makes use of expert systems and simulation in solving dynamic scheduling problems is
(Multiple Choice)
4.8/5
(33)
Which of the following is not tracked by scheduling optimization systems used in retail stores?
(Multiple Choice)
4.9/5
(33)
Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the earliest due date dispatching rule, in which order should the jobs be processed? 

(Multiple Choice)
4.9/5
(43)
An appliance manufacturer assembles icemakers in large batches. The operations manager would like to significantly reduce the batch size. What would you suggest?
(Multiple Choice)
4.8/5
(37)
The following jobs are waiting to be processed at your work center, which cleans valve body castings. Job numbers are assigned sequentially upon arrival in the facility (a missing number means that job does not require your work center). All dates are specified as days from Today.
a. In what sequence should the jobs be processed according to the FCFS scheduling rule?
b. In what sequence should the jobs be processed according to the EDD scheduling rule?
c. In what sequence should the jobs be processed according to the SPT scheduling rule?
d. In what sequence should the jobs be processed according to the LPT scheduling rule?
e. In what sequence should the jobs be processed according to the critical ratio scheduling rule?

(Essay)
4.7/5
(30)
A scheduling technique used to achieve optimum, one-to-one matching of tasks and resources is
(Multiple Choice)
4.9/5
(33)
A work center had actual input of 280 hours and actual output of 270 hours. What is the change in backlog?
(Multiple Choice)
4.8/5
(31)
Showing 1 - 20 of 139