Exam 11: Project Management
Exam 1: Introduction to Quantitative Analysis96 Questions
Exam 2: Probability Concepts and Applications155 Questions
Exam 3: Decision Analysis128 Questions
Exam 4: Regression Models129 Questions
Exam 5: Forecasting138 Questions
Exam 6: Inventory Control Models147 Questions
Exam 7: Linear Programming Models: Graphical and Computer Methods141 Questions
Exam 8: Linear Programming Applications89 Questions
Exam 9: Transportation, Assignment, and Network Models112 Questions
Exam 10: Integer Programming, Goal Programming, and Nonlinear Programming86 Questions
Exam 11: Project Management142 Questions
Exam 12: Waiting Lines and Queuing Theory Models127 Questions
Exam 13: Simulation Modeling94 Questions
Exam 14: Markov Analysis103 Questions
Exam 15: Statistical Quality Control96 Questions
Exam 16: Analytic Hierarchy Process66 Questions
Exam 17: Dynamic Programming86 Questions
Exam 18: Decision Theory and the Normal Distribution62 Questions
Exam 19: Game Theory59 Questions
Exam 20: Mathematical Tools: Determinants and Matrices104 Questions
Exam 21: Calculus-Based Optimization39 Questions
Exam 22: Linear Programming: The Simplex Method98 Questions
Exam 23: Transportation, Assignment, and Network Algorithms120 Questions
Select questions type
Which of the following statements about project crashing is false?
(Multiple Choice)
4.9/5
(37)
Consider the tasks, durations, and predecessor relationships in the following network.Draw the network and answer the questions that follow.
(a)What is the expected duration of the project?
(b)What is the probability of completion of the project before week 42?

(Essay)
4.9/5
(35)
Given the following small project, the critical path is ________ days. 

(Multiple Choice)
4.8/5
(41)
Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.
-Consider the project summarized in Table 11-8.Suppose in addition to the costs shown in the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of the world.Which of these activities should be crashed in an effort to deliver a minimum cost (both project and opportunity cost)project?

(Multiple Choice)
4.8/5
(33)
The first step in planning and scheduling a project is to develop the
(Multiple Choice)
4.8/5
(41)
Table 11-2
The following represents a project with four activities.All times are in weeks.
-According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals.)

(Multiple Choice)
4.8/5
(32)
Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks.What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)
(Multiple Choice)
4.8/5
(35)
The process of smoothing out the utilization of resources in a project is called
(Multiple Choice)
4.8/5
(32)
Table 11-4
The following represents a project with known activity times.All times are in weeks.
-Using the data in Table 11-4, compute the latest finish time for activity E.

(Multiple Choice)
4.9/5
(38)
Table 11-5
-How long could Table 11-5's activity E be delayed without delaying the completion of the project?

(Multiple Choice)
4.8/5
(34)
Table 11-4
The following represents a project with known activity times.All times are in weeks.
-Using the data in Table 11-4, determine the latest time activity A can be finished and not delay any activity?

(Multiple Choice)
4.8/5
(42)
Given:
Determine:
(a)the critical path.
(b)the probability that the project will be completed in 22 weeks.


(Essay)
4.7/5
(40)
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time.What due date should be set?
(Multiple Choice)
4.9/5
(40)
A small software development project has four major activities.The times are estimated and provided in the table below.
(a)What is the expected completion time for this project?
(b)What variance would be used in finding probabilities of finishing by a certain time?

(Essay)
4.7/5
(37)
Showing 21 - 40 of 142
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)