Exam 5: Developing the Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The overall window of time in which a project must be completed is defined by its ____ time and ____ time.

(Multiple Choice)
4.7/5
(41)

Total Slack is sometimes called

(Multiple Choice)
4.8/5
(37)

When considering the availability of resources, it may be necessary to make some assumptions, such as

(Multiple Choice)
4.9/5
(40)

When planning the project, it is important to

(Multiple Choice)
4.9/5
(40)

Project management is a proactive approach to controlling a project to ensure that the project objective is accomplished, even when things do not go according to plan.

(True/False)
4.7/5
(28)

Each activity has two pairs of duration and cost estimates: ____ and ____.

(Multiple Choice)
4.9/5
(40)

The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.Task A takes nine days to be completed instead of seven days.How much slack does the project have now that Task A is finished?

(Multiple Choice)
4.7/5
(41)

In many cases, especially for smaller projects, most activities involve people resources-that is,

(Multiple Choice)
4.9/5
(39)

A change in the estimated duration of any activity on that path will cause a corresponding change in the slack for that path.

(True/False)
4.9/5
(40)

The latest finish time for a specific activity must be the same as or earlier than the earliest of all the latest start times of all the activities emerging directly from that specific activity.

(True/False)
4.8/5
(36)

The ____ time is the shortest estimated length of time in which the activity can be completed.

(Multiple Choice)
4.7/5
(45)

Once this baseline plan is agreed upon by the customer and the contractor or project team, the project work can be performed.

(True/False)
5.0/5
(37)

At the beginning of a longer-term project, it is easier to estimate the duration of

(Multiple Choice)
4.9/5
(41)

The contractor may not want to commit to completing the project by a specific date until the customer has approved the contract.

(True/False)
4.7/5
(27)

As the project progresses, the actual finish times (AFs)of completed activities will determine

(Multiple Choice)
4.8/5
(39)

The sponsor or customer often states the project required completion time in the project charter, RFP, or contract.

(True/False)
4.8/5
(35)

An updated project schedule can be generated regularly that forecasts whether the project will finish ahead of or behind its required completion time.

(True/False)
4.8/5
(43)

The estimated duration should be aggressive and unrealistic.

(True/False)
4.9/5
(38)

Changes requested early in the project always have more impact on schedule and budget than if they are requested later in the project.

(True/False)
4.8/5
(35)

Positive slack indicates the maximum amount of time

(Multiple Choice)
4.9/5
(29)
Showing 41 - 60 of 127
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)