Exam 5: Developing the Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.

(Multiple Choice)
4.9/5
(32)

The estimated duration for each activity must be the total elapsed time,

(Multiple Choice)
4.9/5
(36)

The duration of a task is

(Multiple Choice)
4.8/5
(30)

The latest start time for a specific activity is

(Multiple Choice)
4.9/5
(28)

Schedule updates of the project using actual finish times

(Multiple Choice)
4.9/5
(38)

Agile project management is an approach to ____ product development time while ____ risk through continuous interaction between the customer and small self-organizing teams that produce increments of working product.

(Multiple Choice)
4.8/5
(34)

The Scrum master is ____ as a project manager in that he ____ responsibility for the people on the development team.

(Multiple Choice)
4.8/5
(41)

As a part of the Scrum technique in agile project management, a sprint is usually one to four

(Multiple Choice)
4.8/5
(36)

The ____ trade-off methodology is used to incrementally reduce the project duration with the smallest associated increase in incremental cost.

(Multiple Choice)
5.0/5
(40)

The project team member also referred to as the customer representative and responsible for defining the customer requirements and product features and for ensuring that the development team delivers an end product with the required features is the

(Multiple Choice)
4.9/5
(37)

When changes are agreed upon, a new ____ should be established and used as the benchmark against which actual project performance will be compared.

(Multiple Choice)
4.7/5
(34)

If the project is ahead of schedule, then concentrated efforts should be made to

(Multiple Choice)
4.8/5
(42)

The project control process involves all of the following except

(Multiple Choice)
4.8/5
(44)

The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.Task A takes nine days to be completed instead of seven days.What are the ES and EF times for Task B now that Task A is complete?

(Multiple Choice)
4.9/5
(50)

Throughout a project, changes may occur that have an impact on the schedule.

(True/False)
4.9/5
(31)

One way to determine which activities make up the critical path is to find which ones have the least slack.

(True/False)
4.8/5
(35)

Describe the agile project management for a project where a Scrum master is facilitating the Scrum development process for a software development project.Include a description of the six steps in the agile project management process.

(Essay)
4.8/5
(40)

Free slack is the amount of time a specific activity can be

(Multiple Choice)
4.8/5
(41)

The actual finish time of an activity

(Multiple Choice)
4.9/5
(35)

Latest start time is calculated by

(Multiple Choice)
4.7/5
(34)
Showing 21 - 40 of 127
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)