Exam 5: Developing the Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

This longest path in the overall network diagram is called the network path.

(True/False)
4.8/5
(39)

The amount of slack should determine the priority with which these concentrated efforts are applied.

(True/False)
4.8/5
(42)

The estimated duration for each activity is indicated by a bar spanning the period

(Multiple Choice)
4.8/5
(34)

For large projects that involve several hundred people performing various activities over several years, it is practical to have each person estimate activity durations at the beginning of the project.

(True/False)
4.9/5
(38)

Total slack for the project is the difference between

(Multiple Choice)
4.7/5
(45)

Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.

(Multiple Choice)
4.9/5
(37)

Earliest finish time (EF)is the earliest time by which a specific activity can be completed, calculated

(Multiple Choice)
4.8/5
(39)

The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.How much slack does the project have?

(Multiple Choice)
4.8/5
(27)

The estimated resources required for an activity will influence the estimated duration to perform the activity.

(True/False)
4.8/5
(32)

Free slack of an activity is

(Multiple Choice)
4.9/5
(39)

The project control process must occur regularly throughout the project and include all of the following except

(Multiple Choice)
4.8/5
(29)

At the beginning of every project, it is possible to estimate the durations for all activities with a high level of confidence regarding their accuracy.

(True/False)
5.0/5
(43)

The critical path of a project

(Multiple Choice)
4.9/5
(36)

If the total slack is zero, the activities on the path do not need to be accelerated but cannot be delayed.

(True/False)
4.9/5
(31)

The earliest finish time for an activity

(Multiple Choice)
4.8/5
(42)

If an organization or subcontractor has performed similar projects in the past and has kept records of how long specific activities actually took, these historical data

(Multiple Choice)
4.8/5
(34)

____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time.

(Multiple Choice)
4.8/5
(39)

Analyzing the schedule to determine which areas may need corrective action

(Short Answer)
4.7/5
(37)

People sometimes perform to expectations, their effort will expand to fill the whole number of scheduled days allotted,

(Multiple Choice)
4.8/5
(34)

The estimated duration for an activity must be based on the estimated quantity of resources required to perform the activity.

(True/False)
4.7/5
(36)