Exam 5: Developing the Schedule
Exam 1: Project Management Concepts99 Questions
Exam 2: Identifying and Selecting Projects92 Questions
Exam 3: Developing Project Proposals153 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence166 Questions
Exam 5: Developing the Schedule127 Questions
Exam 6: Resource Utilization45 Questions
Exam 7: Determining Costs, Budget and Earned Value103 Questions
Exam 8: Managing Risk72 Questions
Exam 9: Closing the Project64 Questions
Exam 10: The Project Manager165 Questions
Exam 11: The Project Team275 Questions
Exam 12: Project Communication and Documentation164 Questions
Exam 13: Project Management Organizational Structures109 Questions
Select questions type
This longest path in the overall network diagram is called the network path.
(True/False)
4.8/5
(39)
The amount of slack should determine the priority with which these concentrated efforts are applied.
(True/False)
4.8/5
(42)
The estimated duration for each activity is indicated by a bar spanning the period
(Multiple Choice)
4.8/5
(34)
For large projects that involve several hundred people performing various activities over several years, it is practical to have each person estimate activity durations at the beginning of the project.
(True/False)
4.9/5
(38)
Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.
(Multiple Choice)
4.9/5
(37)
Earliest finish time (EF)is the earliest time by which a specific activity can be completed, calculated
(Multiple Choice)
4.8/5
(39)
The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.How much slack does the project have?
(Multiple Choice)
4.8/5
(27)
The estimated resources required for an activity will influence the estimated duration to perform the activity.
(True/False)
4.8/5
(32)
The project control process must occur regularly throughout the project and include all of the following except
(Multiple Choice)
4.8/5
(29)
At the beginning of every project, it is possible to estimate the durations for all activities with a high level of confidence regarding their accuracy.
(True/False)
5.0/5
(43)
If the total slack is zero, the activities on the path do not need to be accelerated but cannot be delayed.
(True/False)
4.9/5
(31)
If an organization or subcontractor has performed similar projects in the past and has kept records of how long specific activities actually took, these historical data
(Multiple Choice)
4.8/5
(34)
____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time.
(Multiple Choice)
4.8/5
(39)
Analyzing the schedule to determine which areas may need corrective action
(Short Answer)
4.7/5
(37)
People sometimes perform to expectations, their effort will expand to fill the whole number of scheduled days allotted,
(Multiple Choice)
4.8/5
(34)
The estimated duration for an activity must be based on the estimated quantity of resources required to perform the activity.
(True/False)
4.7/5
(36)