Free slack is calculated by finding the lowest of the values of total slack for all the activities entering into a specific activity and then

(Multiple Choice)
4.8/5
(33)

With respect to the project schedule, changes can result in any of the following except

(Multiple Choice)
5.0/5
(35)

Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.

(Multiple Choice)
4.9/5
(37)

In order to establish a basis from which to calculate a schedule using the estimated durations for the activities, it is necessary to

(Multiple Choice)
4.8/5
(41)

The ES and EF times are determined by calculating forward, that is, by

(Multiple Choice)
4.8/5
(24)

The amount of ____ should determine the priority with which concentrated efforts are applied.

(Multiple Choice)
4.8/5
(39)

When estimating resources for activities to estimate the activity's duration, the

(Multiple Choice)
5.0/5
(40)

Total slack for a project that is negative represents the amount of time that

(Multiple Choice)
4.8/5
(40)

When estimating the types and quantities of resources required for each specific activity, it is valuable to involve a person who

(Multiple Choice)
4.9/5
(40)

The project control process starts with establishing a baseline plan that shows how the project scope will be accomplished beyond the schedule and over budget.

(True/False)
4.9/5
(40)

The ____ is the estimated cost to complete the activity in the normal time.

(Multiple Choice)
4.9/5
(37)

A regular ____ should be established for comparing actual progress with planned progress.

(Multiple Choice)
4.8/5
(38)

The ____ of completed activities will determine the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the total slack.

(Multiple Choice)
4.8/5
(33)

Negative slack indicates a lack of slack over the entire project and the amount of time

(Multiple Choice)
4.9/5
(39)

A Gantt chart is the often the name for the network diagram tool for looping and laddering.

(True/False)
5.0/5
(40)

The facilitator for the Scrum development process during a sprint whose primary job is to take actions to remove or reduce any obstacles, barriers, or constraints that are impeding progress of the development team toward accomplishing their work tasks and that may negatively impact the successful production and demonstration of a deliverable working product increment by the end of the sprint time is the

(Multiple Choice)
4.8/5
(40)

Total slack is calculated by ____.

(Multiple Choice)
4.9/5
(44)

It is necessary to monitor the progress to ensure that everything is going according to the plan.

(True/False)
5.0/5
(39)

Calculate the latest finish for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.

(Multiple Choice)
4.9/5
(41)

Earliest start time (ES)is the earliest time at which a specific activity can begin

(Multiple Choice)
4.9/5
(29)