Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence
Exam 1: Project Management Concepts99 Questions
Exam 2: Identifying and Selecting Projects92 Questions
Exam 3: Developing Project Proposals153 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence166 Questions
Exam 5: Developing the Schedule127 Questions
Exam 6: Resource Utilization45 Questions
Exam 7: Determining Costs, Budget and Earned Value103 Questions
Exam 8: Managing Risk72 Questions
Exam 9: Closing the Project64 Questions
Exam 10: The Project Manager165 Questions
Exam 11: The Project Team275 Questions
Exam 12: Project Communication and Documentation164 Questions
Exam 13: Project Management Organizational Structures109 Questions
Select questions type
Describe the quality standards that must be included or referenced in the quality plan.
(Essay)
4.7/5
(33)
In the network diagram for the following list, what activity immediately follows activity D? Activity
Immediate Predecessor
A
-
B
A
C
A
D
B,C
E
C
F
D
G
E
H
F
I
G,H
J
I
(Multiple Choice)
4.8/5
(27)
A(n)____ is defined as a piece of work that consumes time.
(Multiple Choice)
4.8/5
(31)
The ____ is a roadmap that displays how all the specific activities fit together to accomplish the project work scope.
(Multiple Choice)
4.8/5
(37)
Expected benefits, which will result from implementation of the project and define success, establish
(Multiple Choice)
4.9/5
(41)
The project scope document is valuable for establishing a common understanding among project stakeholders regarding the scope of the project.
(True/False)
4.8/5
(28)
It is common to progressively elaborate the network diagram
(Multiple Choice)
4.9/5
(24)
In the network diagram for the following list, what activity immediately follows activity E? Activity
Immediate Predecessor
A
-
B
A
C
A
D
B,C
E
D
F
D
G
E,F
H
G
(Multiple Choice)
4.8/5
(42)
The ____ may include a high-level WBS in a graphic chart format or as an indentured list of the work elements and associated deliverables.
(Multiple Choice)
4.9/5
(37)
It is important to plan for ____ in performing the project to assure that the work is done according to specifications and applicable standards and that deliverables meet acceptance criteria.
(Multiple Choice)
4.8/5
(37)
Having a written quality plan at the outset of a project is extremely beneficial because it guarantees against incurring additional costs and schedule extensions due to rework caused by work and deliverables that fail to meet quality requirements and customer expectations.
(True/False)
4.9/5
(46)
The work packages are at a level ____ can be assigned responsibility and accountability for accomplishing the work package.
(Multiple Choice)
4.9/5
(40)
An understanding of project deliverables would also be a setback to developing a good working relationship with the customer.
(True/False)
5.0/5
(33)
A responsibility assignment matrix is used to designate the individuals responsible for accomplishing the work items in the work breakdown structure.
(True/False)
5.0/5
(38)
____ determines what needs to be done, who will do it, how long it will take, and how much it will cost.
(Multiple Choice)
4.9/5
(32)
The ____ is the tangible end product that the project team or contractor must produce and deliver in order for the sponsor or customer to achieve the expected benefits from implementing the project.
(Multiple Choice)
4.7/5
(28)
A written quality control plan at the outset of the project
(Multiple Choice)
4.8/5
(35)
It is important to document the detailed requirements in the ____ in order to establish a clear understanding with the sponsor or customer.
(Multiple Choice)
5.0/5
(38)
Showing 141 - 160 of 166