Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence
Exam 1: Project Management Concepts99 Questions
Exam 2: Identifying and Selecting Projects92 Questions
Exam 3: Developing Project Proposals153 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence166 Questions
Exam 5: Developing the Schedule127 Questions
Exam 6: Resource Utilization45 Questions
Exam 7: Determining Costs, Budget and Earned Value103 Questions
Exam 8: Managing Risk72 Questions
Exam 9: Closing the Project64 Questions
Exam 10: The Project Manager165 Questions
Exam 11: The Project Team275 Questions
Exam 12: Project Communication and Documentation164 Questions
Exam 13: Project Management Organizational Structures109 Questions
Select questions type
____ in a network diagram will allow the project to be completed in the shortest possible time while making the best use of available resources (the experts).
(Multiple Choice)
4.9/5
(29)
Draw network diagram for the following project.
Activity
Immediate Predecessor
A
-
B
A
C
A
D
B,C
E
C
F
D
G
E
H
F
I
G,H
J
I
(Essay)
4.9/5
(35)
The agreed-upon project scope document establishes the baseline for any changes that may be made to the scope during the performance of the project.
(True/False)
4.8/5
(35)
The ____ may need to describe certain inspection techniques, testing procedures, or specific testing equipment or facilities that must be used.
(Multiple Choice)
4.8/5
(35)
The quality plan may also state that suppliers must provide documentation certifying that the materials they supply meet certain required specifications.
(True/False)
4.9/5
(33)
The major work elements defined in the statement of work section along with the detailed list of deliverables provide the basis for creating a
(Multiple Choice)
4.8/5
(45)
For large or complex projects, it may be difficult for one individual to determine all the work elements to include in the work breakdown structure.
(True/False)
4.8/5
(29)
An activity, also referred to as a task, is a defined piece of work that consumes effort by people and not time.
(True/False)
4.8/5
(41)
Ambiguous acceptance criteria for all deliverables are important because they are the basis for verifying that the project scope has been completed in accordance with the customer's requirements and expectations.
(True/False)
4.8/5
(42)
Given the following activities, draw the network diagram for the activities in the project.
Activity
Immediate Predecessor
A
-
B
A
C
A
D
B,C
E
D
F
D
G
E,F
H
G
(Essay)
4.9/5
(35)
In the network diagram for the following list, what activity immediately follows activity E? Activity
Immediate Predecessor
A
-
B
A
C
A
D
B,C
E
C
F
D
G
E
H
F
I
G,H
J
I
(Multiple Choice)
4.8/5
(41)
The project manager should involve every project member in developing the WBS to have special expertise, knowledge, or experience that will help develop a more comprehensive and complete WBS.
(True/False)
4.8/5
(33)
A project scope statement defines the sequence of how the activities will get done.
(True/False)
4.9/5
(37)
The responsibility assignment matrix may use a P to designate ____ responsibility and an S to indicate ____ responsibility for a specific work item.
(Multiple Choice)
4.9/5
(38)
A ____ shows their appropriate sequence and defines the dependent relationships indicating how the activities need to be performed to accomplish the overall project work scope and produce the deliverables.
(Multiple Choice)
4.7/5
(36)
Activities in a network diagram have ____, that is, they are linked in a logical sequence to show which activities must be finished before others can start.
(Multiple Choice)
5.0/5
(37)
____ are the products or outputs that the project team or contractor will produce and provide to the customer during and at the completion of the performance of the project.
(Multiple Choice)
4.8/5
(30)
Showing 61 - 80 of 166
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)