The WBS should be decomposed to a level that identifies individual work packages for

(Multiple Choice)
4.8/5
(35)

The lowest-level work item of any one branch is called

(Multiple Choice)
4.8/5
(34)

If the scope seems much less than originally anticipated by the customer, the customer and contractor would have to agree on increasing the budget, extending the schedule, reducing the scope, or some combination thereof.

(True/False)
4.9/5
(31)

Acceptance criteria for all project deliverables must be ____ than what is stated in the project charter or request for proposal.

(Multiple Choice)
4.9/5
(42)

The key to quality control is to wait until all the work is completed before checking or inspecting for quality.

(True/False)
4.8/5
(35)

The WBS usually indicates the organization or individual assigned responsibility for performance and completion of each work item.

(True/False)
4.8/5
(29)

The work breakdown structure can include specifications regarding size, color, weight, or performance parameters, such as speed, uptime, throughput, processing time, or operating temperature range, that the project result must satisfy.

(True/False)
4.8/5
(32)

A WBS subdivides the project into smaller pieces called ____.

(Multiple Choice)
4.8/5
(26)

Multiple individuals should be designated the lead, or primary, responsibility for each work item.

(True/False)
4.8/5
(32)

Unlike ____ separate(s)the planning and scheduling functions.

(Multiple Choice)
4.8/5
(35)

The project objective must be clearly defined and agreed upon by the

(Multiple Choice)
4.8/5
(29)

There can be situations where the project objective needs to be modified as the project proceeds.

(True/False)
4.9/5
(38)

With the quality plan in place including procedures for the application of appropriate quality tools and techniques, quality can then be monitored and controlled.

(True/False)
4.8/5
(31)

In preparing a network diagram, drawing activities in a ____ is not acceptable because it portrays a path of activities that perpetually repeats itself.

(Multiple Choice)
4.9/5
(33)

The project quality plan should state which tools and techniques to use and when.

(True/False)
4.8/5
(31)

Standard subnetworks should be developed for those portions of projects for which

(Multiple Choice)
4.9/5
(25)

The network diagram defines the sequence of how the activities will get done and

(Multiple Choice)
4.8/5
(32)

Activities should ____ the time intervals at which actual project progress will be reviewed and compared to planned progress.

(Multiple Choice)
5.0/5
(42)

List at least three ways information to further refine the customer requirements in the project charter or RFP can be obtained or collected.

(Essay)
4.8/5
(40)

A task is a piece of work that consumes time.Which statement is false?

(Multiple Choice)
4.7/5
(34)