Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, structure, and Culture106 Questions
Exam 3: Project Selection and Portfolio Management116 Questions
Exam 4: Leadership and the Project Manager130 Questions
Exam 5: Scope Management116 Questions
Exam 6: Project Team Building, conflict, and Negotiation123 Questions
Exam 7: Risk Management114 Questions
Exam 8: Cost Estimation and Budgeting114 Questions
Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path118 Questions
Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks110 Questions
Exam 11: Critical Chain Project Scheduling117 Questions
Exam 12: Resource Management93 Questions
Exam 13: Project Evaluation and Control117 Questions
Exam 14: Project Closeout and Termination120 Questions
Select questions type
Use the information in the table to sketch the network and compute early and late start times.


(Essay)
4.8/5
(36)
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.9/5
(39)
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
(True/False)
4.8/5
(36)
What is laddering and what advantages can be gained from its use in project management?
(Essay)
4.8/5
(31)
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project? 

(Multiple Choice)
4.7/5
(29)
Use the network diagram and activity lengths in the nodes to determine the late start time for activity F. 

(Multiple Choice)
4.8/5
(47)
A(n)________ is a project schedule whose start and finish dates reflect expected resource availability.
(Essay)
4.8/5
(40)
The length of time expected to complete an activity assuming that its development proceeds normally is called the:
(Multiple Choice)
4.9/5
(35)
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path? 

(Multiple Choice)
4.9/5
(37)
Use the information in the table to determine the late start time for Activity E. 

(Multiple Choice)
4.8/5
(28)
The PERT technique assumes that durations are more deterministic.
(True/False)
4.8/5
(43)
Thanks to excessive dilly dallying,the subcontractor grossly exceeded the slack on his portion of the project,resulting in ________.
(Essay)
4.9/5
(30)
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?


(Essay)
4.9/5
(40)
The best candidate activities for shortening the overall project are:
(Multiple Choice)
4.8/5
(33)
What is the slack time for Activity B given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.8/5
(27)
In order to reduce the length of a project,it would be wise to shorten:
(Multiple Choice)
4.9/5
(32)
Showing 81 - 100 of 118
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)