Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, structure, and Culture106 Questions
Exam 3: Project Selection and Portfolio Management116 Questions
Exam 4: Leadership and the Project Manager130 Questions
Exam 5: Scope Management116 Questions
Exam 6: Project Team Building, conflict, and Negotiation123 Questions
Exam 7: Risk Management114 Questions
Exam 8: Cost Estimation and Budgeting114 Questions
Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path118 Questions
Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks110 Questions
Exam 11: Critical Chain Project Scheduling117 Questions
Exam 12: Resource Management93 Questions
Exam 13: Project Evaluation and Control117 Questions
Exam 14: Project Closeout and Termination120 Questions
Select questions type
Activities that can be worked on simultaneously are ________ activities.
(Essay)
4.9/5
(28)
The late finish times are determined by taking a(n)________ through the network.
(Essay)
4.9/5
(42)
Use the network diagram and activity lengths in the nodes to determine the slack time for activity D. 

(Multiple Choice)
4.7/5
(39)
At a merge point in a forward pass,the largest preceding early finish becomes the early start for that node.
(True/False)
4.8/5
(37)
Because an activity's pessimistic estimate may represent a much greater deviation from the most likely time than its optimistic estimate,the ________ better represents the distribution of possible alternative durations.
(Essay)
4.8/5
(41)
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C. 

(Multiple Choice)
4.8/5
(40)
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. 

(Multiple Choice)
4.8/5
(37)
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.7/5
(32)
Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G. 

(Multiple Choice)
4.7/5
(31)
Activities C,D,and E in the project represented by the network are to be hammocked.What are the late start and early finish times of the hammock activity? 

(Multiple Choice)
4.8/5
(33)
What is the slack time for Activity C given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.7/5
(40)
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity? 

(Multiple Choice)
4.8/5
(40)
Based on the activity network pictured,what is the best statement? 

(Multiple Choice)
4.8/5
(41)
An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time.If the activity variance is 10,what is the expected time?
(Multiple Choice)
4.7/5
(34)
What is the background of CPM and PERT? What are the differences between the two techniques?
(Essay)
4.9/5
(32)