Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

Activities that can be worked on simultaneously are ________ activities.

(Essay)
4.9/5
(28)

The late finish times are determined by taking a(n)________ through the network.

(Essay)
4.9/5
(42)

Use the network diagram and activity lengths in the nodes to determine the slack time for activity D. Use the network diagram and activity lengths in the nodes to determine the slack time for activity D.

(Multiple Choice)
4.7/5
(39)

In general,the better candidates for shortening are:

(Multiple Choice)
4.8/5
(36)

________ activities have two or more immediate successors.

(Short Answer)
4.9/5
(45)

In the beta distribution,the longer tail is located ________.

(Essay)
4.7/5
(28)

At a merge point in a forward pass,the largest preceding early finish becomes the early start for that node.

(True/False)
4.8/5
(37)

Because an activity's pessimistic estimate may represent a much greater deviation from the most likely time than its optimistic estimate,the ________ better represents the distribution of possible alternative durations.

(Essay)
4.8/5
(41)

Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C. Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.

(Multiple Choice)
4.8/5
(40)

Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

(Multiple Choice)
4.8/5
(37)

What is the late finish time for Activity D given the activity times and precedence requirements shown in the table? What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?

(Multiple Choice)
4.7/5
(32)

There is no slack on the project ________.

(Essay)
4.9/5
(32)

Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G. Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.

(Multiple Choice)
4.7/5
(31)

Activities C,D,and E in the project represented by the network are to be hammocked.What are the late start and early finish times of the hammock activity? Activities C,D,and E in the project represented by the network are to be hammocked.What are the late start and early finish times of the hammock activity?

(Multiple Choice)
4.8/5
(33)

What is the slack time for Activity C given the activity times and precedence requirements shown in the table? What is the slack time for Activity C given the activity times and precedence requirements shown in the table?

(Multiple Choice)
4.7/5
(40)

A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity? A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?

(Multiple Choice)
4.8/5
(40)

The variance of an activity is given by:

(Multiple Choice)
4.9/5
(31)

Based on the activity network pictured,what is the best statement? Based on the activity network pictured,what is the best statement?

(Multiple Choice)
4.8/5
(41)

An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time.If the activity variance is 10,what is the expected time?

(Multiple Choice)
4.7/5
(34)

What is the background of CPM and PERT? What are the differences between the two techniques?

(Essay)
4.9/5
(32)
Showing 41 - 60 of 118
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)