Exam 16: Lean Operations
Exam 1: Operations and Productivity134 Questions
Exam 2: Operations Strategy in a Global Environment145 Questions
Exam 3: Project Management131 Questions
Exam 4: Forecasting151 Questions
Exam 5: Design of Goods and Services136 Questions
Exam 6: Managing Quality139 Questions
Exam 7: Process Strategy and Sustainability141 Questions
Exam 8: Location Strategies149 Questions
Exam 9: Layout Strategies171 Questions
Exam 10: Human Resources, Job Design, and Work Measurement202 Questions
Exam 11: Supply-Chain Management152 Questions
Exam 12: Inventory Management178 Questions
Exam 13: Aggregate Planning144 Questions
Exam 14: Material Requirements Planning Mrp and Erp184 Questions
Exam 15: Short-Term Scheduling149 Questions
Exam 16: Lean Operations147 Questions
Exam 17: Maintenance and Reliability139 Questions
Exam 18: Decision-Making Tools107 Questions
Exam 19: Linear Programming110 Questions
Exam 20: Transportation Models104 Questions
Exam 21: Waiting-Line Models145 Questions
Exam 22: Learning Curves121 Questions
Exam 23: Simulation102 Questions
Exam 24: Supply Chain Management Analytics65 Questions
Exam 25: Sustainability in the Supply Chain11 Questions
Exam 26: Statistical Process Control166 Questions
Exam 27: Capacity and Constraint Management117 Questions
Select questions type
The cook in a fast-food restaurant knows that 2 hamburger patties and an order of fries should be started for each car that is waiting in line. This is best an example of
(Multiple Choice)
4.9/5
(38)
JIT brings about competitive advantage by faster response to the customer regardless of cost.
(True/False)
4.8/5
(48)
Which of the following is specifically characterized by the elimination of waste through a focus on exactly what the customer wants?
(Multiple Choice)
4.9/5
(35)
If the goals of JIT partnerships are met, which of the following is a result?
(Multiple Choice)
4.8/5
(40)
A bakery uses 9 containers that each hold 6 cakes. If daily demand is 40 cakes and lead time is 1 day determine the safety stock.
(Essay)
4.8/5
(42)
The 5Ss-sort/segregate, simplify/straighten, shine/sweep, standardize, and sustain/self discipline-are important to lean production because they act as a means to reduce waste.
(True/False)
4.9/5
(40)
Which of the following statements regarding a pull system is true?
(Multiple Choice)
5.0/5
(39)
Which one of the following scenarios represents the use of a kanban to reduce inventories?
(Multiple Choice)
4.8/5
(33)
Which of the following is the author of the phrase "Inventory is evil"?
(Multiple Choice)
4.9/5
(28)
Labor cost for set-up is $500/hour. If the plant plans on level material use and operates 50 days per year, determine the time it takes to setup.
Annual demand 5000 Daily production 1000 Lot size 700 Holding cost \ 25
(Essay)
4.8/5
(24)
A bakery uses 5 containers that hold 3 cakes. Daily demand is 10 cakes and safety stock is 5 cakes. What is the lead time?
(Short Answer)
4.9/5
(32)
Which of the following statements regarding JIT in services is true?
(Multiple Choice)
4.7/5
(46)
________ is a JIT concept that results in material being produced only when requested and moved to where it is needed just as it is needed.
(Short Answer)
5.0/5
(34)
Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 10 kanbans how many computers should each one hold?
(Multiple Choice)
4.8/5
(40)
The Toyota Production System requires that activities have built-in, automatic tests so that gaps between expectations and actuality are immediately evident.
(True/False)
4.8/5
(34)