Exam 20: Resource Planning
Exam 1: Operations Management58 Questions
Exam 2: Quality Management74 Questions
Exam 3: Statistical Process Control112 Questions
Exam 4: Operational Decision-Making Tools: Acceptance Sampling28 Questions
Exam 5: Product Design83 Questions
Exam 6: Service Design80 Questions
Exam 7: Processes and Technology73 Questions
Exam 8: Capacity and Facilities Design85 Questions
Exam 9: Operational Decision-Making Tools: Facility Location Models21 Questions
Exam 10: Human Resources79 Questions
Exam 11: Operational Decision-Making Tools: Work Measurement31 Questions
Exam 12: Project Management85 Questions
Exam 13: Supply Chain Management: Strategy and Design56 Questions
Exam 14: Global Supply Chain Procurement and Distribution69 Questions
Exam 15: Forecasting85 Questions
Exam 16: Inventory Management78 Questions
Exam 17: Operational Decision-Making Tools: Simulation15 Questions
Exam 18: The Sales and Operations Planning Process76 Questions
Exam 19: Operational Decision-Making Tools: Linear Programming29 Questions
Exam 20: Resource Planning82 Questions
Exam 21: Lean Systems78 Questions
Exam 22: Scheduling78 Questions
Select questions type
For information concerning on-hand quantities,lot sizes,and lead time,figures can be found in the master production schedule (MPS).
(True/False)
4.8/5
(31)
The optimal time required to manufacture a product is called its cumulative lead time.
(True/False)
4.9/5
(44)
A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period.
If EOQ lot sizing is used to set the minimum order quantity,then the projected on hand quantity at the end of period 3 would be

(Multiple Choice)
4.9/5
(32)
A matrix is used to organize and display the information generated by the MRP process.
(True/False)
4.9/5
(41)
Given the following MRP matrix for Item E:
The planned order releases for period 4 would be

(Multiple Choice)
4.9/5
(35)
The MRP process of determining requirements for lower level items based on the master production schedule is referred to as
(Multiple Choice)
4.8/5
(42)
Because the item master file is an input into the MRP process,it should be updated to reflect any revisions or changes.
(True/False)
4.9/5
(32)
Effective capacity is determined by multiplying the rated capacity by utilization and efficiency.
(True/False)
4.8/5
(46)
Very simple products typically do not require material requirements planning (MRP)to plan production or monitor inventory levels.
(True/False)
4.9/5
(32)
Material requirements planning (MRP)is more useful for simple products and less useful for complex products.
(True/False)
4.8/5
(39)
Given the following Product Structure Record:
The number of G's required for each A would be

(Multiple Choice)
4.9/5
(35)
The last stage in ERP implementation involves analyzing business processes.
(True/False)
4.9/5
(35)
Given the following Product Structure Record:
The number of F's required for each A would be

(Multiple Choice)
4.9/5
(33)
Given the following MRP matrix for Item C:
If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Projected on Hand at the end of period 7 would be

(Multiple Choice)
4.8/5
(45)
An enterprise resource planning (ERP)system shares information across functional areas.
(True/False)
4.8/5
(35)
All of the following can be used for underloaded conditions except
(Multiple Choice)
4.7/5
(38)
Load levelling is used to resolve underloaded and overloaded capacity conditions.
(True/False)
4.8/5
(32)