Exam 12: Project Management
Exam 1: Operations Management58 Questions
Exam 2: Quality Management74 Questions
Exam 3: Statistical Process Control112 Questions
Exam 4: Operational Decision-Making Tools: Acceptance Sampling28 Questions
Exam 5: Product Design83 Questions
Exam 6: Service Design80 Questions
Exam 7: Processes and Technology73 Questions
Exam 8: Capacity and Facilities Design85 Questions
Exam 9: Operational Decision-Making Tools: Facility Location Models21 Questions
Exam 10: Human Resources79 Questions
Exam 11: Operational Decision-Making Tools: Work Measurement31 Questions
Exam 12: Project Management85 Questions
Exam 13: Supply Chain Management: Strategy and Design56 Questions
Exam 14: Global Supply Chain Procurement and Distribution69 Questions
Exam 15: Forecasting85 Questions
Exam 16: Inventory Management78 Questions
Exam 17: Operational Decision-Making Tools: Simulation15 Questions
Exam 18: The Sales and Operations Planning Process76 Questions
Exam 19: Operational Decision-Making Tools: Linear Programming29 Questions
Exam 20: Resource Planning82 Questions
Exam 21: Lean Systems78 Questions
Exam 22: Scheduling78 Questions
Select questions type
Indirect costs always increase as a project's duration decreases.
(True/False)
4.9/5
(35)
Microsoft Project is a software package that supports PERT but not CPM.
(True/False)
4.9/5
(33)
Project scope involves a set of procedures for anticipating and assessing uncertainties that might increase the risk of delaying the project.
(True/False)
4.7/5
(33)
Crashing activates with positive slack reduces a project's duration.
(True/False)
4.8/5
(37)
Using Table 9.3,the latest start (LS)time for activity D is
(Multiple Choice)
4.9/5
(41)
In general,the latest finish time for an activity is equal to
(Multiple Choice)
4.9/5
(35)
Using Table 9.2,the probability that the project will take longer than 33 weeks to complete is approximately
(Multiple Choice)
4.8/5
(23)
The estimated variance for an activity with a most likely time (m)equal to 11 days,the optimistic time (a)equal to 6 days,and the pessimistic time (b)equal to 18 days is
(Multiple Choice)
4.8/5
(39)
Using Table 9.1,the amount of slack associated with activity C is
(Multiple Choice)
4.9/5
(36)
With an activity-on-node (AON)network diagram,the nodes indicate the precedence relationships and the arrows represent the project's activities.
(True/False)
4.7/5
(36)
In general,crashing costs decrease as a project's duration is shortened.
(True/False)
4.8/5
(44)
Why have projects taken on a more crucial role in operations management?
(Essay)
4.8/5
(37)
Managing quality is not an important part of project management.
(True/False)
4.8/5
(35)
Project planning involves a set of procedures for monitoring and evaluating progress and performance.
(True/False)
4.8/5
(42)
Using Table 9.2,the variance of the project's total completion time is
(Multiple Choice)
4.8/5
(33)
A work breakdown structure provides a common understanding of and justification for a project.
(True/False)
4.7/5
(38)
The principles of total quality management (TQM)cannot be applied to project management.
(True/False)
4.8/5
(38)
One disadvantage of a Gantt chart,especially for large projects,is that it does not
(Multiple Choice)
4.9/5
(40)
A dummy activity is an activity inserted into the network diagram to show a precedence relationship,but does not represent any passage of time.
(True/False)
4.8/5
(33)