Exam 13: Sales and Operations Planning
Exam 1: Introduction to Managing Operations Across the Supply Chain40 Questions
Exam 2: Operations and Supply Chain Strategy25 Questions
Exam 3: Managing Processes and Capacity29 Questions
Exam 3: A: Process Mapping and Analysis31 Questions
Exam 4: Productprocess Innovation43 Questions
Exam 5: Manufacturing and Service Process Structures53 Questions
Exam 6: Managing Quality44 Questions
Exam 6: A: Quality Improvement Tools51 Questions
Exam 7: Managing Inventories32 Questions
Exam 8: Lean Systems57 Questions
Exam 9: Customer Service Management59 Questions
Exam 10: Sourcing and Supply Management50 Questions
Exam 11: Logistics Management39 Questions
Exam 12: Demand Planning: Forecasting and Demand Management44 Questions
Exam 13: Sales and Operations Planning36 Questions
Exam 14: Materials and Resource Requirements Planning33 Questions
Exam 15: Project Management34 Questions
Exam 15: A: Advanced Methods for Project Scheduling40 Questions
Exam 16: Sustainable Operations Management Preparing for the Future39 Questions
Select questions type
The figure below shows the tasks required to complete a project and the expected duration for each task.
How long should we expect it to take to complete this project?

(Multiple Choice)
4.8/5
(43)
A project manager usually has the greatest ability to affect social and technical success factors of a project in what stage of the project?
(Multiple Choice)
4.8/5
(34)
Zanda Corp.has decided that it needs a project team to implement a new ERP system.It wants the system implemented as soon as possible.Given this criterion,Zanda should choose a:
(Multiple Choice)
4.9/5
(41)
The network diagram below shows the five tasks required to complete a project and the associated times for those tasks.
Which task has the greatest amount of slack?

(Multiple Choice)
4.8/5
(37)
Colson Corp.has planned a simple project with four tasks.The task information for the project is shown below:
What is the estimated completion time for the project?

(Multiple Choice)
4.8/5
(39)
The network diagram below shows the five tasks required to complete a project and the associated times for those tasks.
Which of the following identifies the critical path tasks?

(Multiple Choice)
4.8/5
(38)
A primary advantage of a functional project organizational structure is:
(Multiple Choice)
4.9/5
(38)
Project manager Bill Jones has determined that task R has a high variation between "best case" and "worst case" estimated durations.Task R is probably a good candidate for:
(Multiple Choice)
4.8/5
(40)
The project organizational structure that provides the greatest balance between speed and efficiency is:
(Multiple Choice)
4.8/5
(49)
A method for estimating the impacts of uncertainty on project tasks is:
(Multiple Choice)
4.9/5
(38)
Which of the following is NOT a good reason to terminate (kill)a project?
(Multiple Choice)
4.8/5
(31)
Joe Jones is a project manager on a major installation.He has been asked to provide weekly status reports on the project schedule.Joe should consider using which of the following?
(Multiple Choice)
4.9/5
(37)
Task X is expected to take three days to complete.The maximum (latest)earliest finish date for any predecessors to task X is 10.Therefore,the earliest finish for task X is:
(Multiple Choice)
4.8/5
(40)
Showing 21 - 36 of 36
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)