Exam 9: Location and Layout

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Table 9.18 A company desires to set up a line to produce 60 units per hour. The work elements and their precedence relationships are as follows. Work Element Time (sec) Immediate Predecessor(s) 1 40 -- 2 30 1 3 50 1 4 40 2 5 6 2 6 25 3 7 15 3 8 20 4,5 9 18 6,7 10 30 8,9 -Use the information in Table 9.18.What is the theoretical minimum number of stations versus the number of stations required using the longest work-element time method?

(Multiple Choice)
4.8/5
(38)

A(n)________ layout combines elements of both a product and process focus.

(Short Answer)
4.9/5
(33)

Which one of the following statements about distance measures is best?

(Multiple Choice)
4.7/5
(25)

One common performance criteria for layouts is capital investment.

(True/False)
4.9/5
(35)

Which of the following usually is an advantage of on-site expansion,compared to building a new facility?

(Multiple Choice)
4.9/5
(39)

Table 9.16 Balance the following lines for an output rate of 5 pieces per hour, using the longest work-element time rule. The times are in minutes (not seconds). Work Element Time (min) Immediate Predecessor(s) A 7 -- B 5 -- C 3 -- D 4 -- E 2 A, B F 5 C G 6 D H 7 E, F I 11 F, G J 4 H, I -Use the information from Table 9.16.At what station is task F performed?

(Multiple Choice)
4.9/5
(34)

Which of the following statements on locating new U.S.manufacturing plants is best?

(Multiple Choice)
4.8/5
(38)

Briefly explain the series of steps typically followed in the process of selecting a new facility location from several possible sites.

(Essay)
4.8/5
(47)

________ are the smallest units of work that can be performed independently.

(Short Answer)
4.9/5
(41)

Table 9.17 The Pennsylvania Appliance company is installing an assembly line to produce vacuum cleaners, and you, as an operations manager, are responsible for balancing the line. The work elements to be performed are listed, along with their items and immediate predecessors. Work Element Time (sec) Immediate Predecessor(s) 60 -- 40 30 20 40 60 70 50 , 20 60 , -Use the information in Table 9.17.The company is planning to operate two shifts per day,eight hours per shift.If the desired output rate of the line is 480 units per day,what is the cycle time?

(Multiple Choice)
4.8/5
(46)

Table 9.7 Sagebrush Company has four warehouses (A, B, C, and D) that require monthly shipments of 250, 200, 300, and 200 units per month, respectively. Its three plants (1, 2, and 3) have monthly capacities of 300, 400, and 250, respectively. Shipping costs (in $) follow. A blank transportation method tableau is provided below. Warehouse Plant 1 17 16 16 16 2 15 18 16 17 3 18 15 18 16  Table 9.7 Sagebrush Company has four warehouses (A, B, C, and D) that require monthly shipments of 250, 200, 300, and 200 units per month, respectively. Its three plants (1, 2, and 3) have monthly capacities of 300, 400, and 250, respectively. Shipping costs (in $) follow. A blank transportation method tableau is provided below. Warehouse   \begin{array} { | c | c | c | c | c | }  \hline \text { Plant } & \mathrm { A } & \mathrm { B } & \mathrm { C } & \mathrm { D } \\ \hline 1 & 17 & 16 & 16 & 16 \\ 2 & 15 & 18 & 16 & 17 \\ 3 & 18 & 15 & 18 & 16 \\ \hline \end{array}      -Use the information in Table 9.7.What can be said about a plan that ships 200 units from 1 to A,100 units from 1 to B,100 units from 2 to B,300 units from 2 to C,and 250 units from 3 to D? -Use the information in Table 9.7.What can be said about a plan that ships 200 units from 1 to A,100 units from 1 to B,100 units from 2 to B,300 units from 2 to C,and 250 units from 3 to D?

(Multiple Choice)
4.8/5
(41)

Which one of the following statements about layout is best?

(Multiple Choice)
4.8/5
(36)

When volumes are high,an advantage of flexible-flow layouts over line-flow layouts is faster processing rates.

(True/False)
4.9/5
(35)

Table 9.4 Table 7.4 A company has determined the "demand points" and their relative locations as follows: Coordinates Demand Point Demand 10 10 100 10 20 200 15 10 150 20 10 200 -Using the information in Table 9.4.If a company desires to locate a manufacturing facility at the center of gravity,what would be the x- and y-coordinates of the facility?

(Multiple Choice)
4.9/5
(35)

A company desires to locate a new facility.Based on preliminary analysis,the choice has been reduced to four locations: A,B,C,and D.These four locations were rated on a scale from 1 (worst)to 10 (best)on each of four criteria.Each criterion was also weighted to indicate its importance (i.e.,the higher the weight,the more important).The list of ratings and weights follows. Location Factor Weight A B C D Wages 0.40 7 5 3 5 Labor Climate 0.35 6 5 9 5 Local Regulation 0.15 3 4 3 2 Weather 0.10 2 8 6 9 Based on weighted scores,where should the company locate its new facilities?

(Essay)
4.7/5
(43)

Table 9.7 Sagebrush Company has four warehouses (A, B, C, and D) that require monthly shipments of 250, 200, 300, and 200 units per month, respectively. Its three plants (1, 2, and 3) have monthly capacities of 300, 400, and 250, respectively. Shipping costs (in $) follow. A blank transportation method tableau is provided below. Warehouse Plant 1 17 16 16 16 2 15 18 16 17 3 18 15 18 16  Table 9.7 Sagebrush Company has four warehouses (A, B, C, and D) that require monthly shipments of 250, 200, 300, and 200 units per month, respectively. Its three plants (1, 2, and 3) have monthly capacities of 300, 400, and 250, respectively. Shipping costs (in $) follow. A blank transportation method tableau is provided below. Warehouse   \begin{array} { | c | c | c | c | c | }  \hline \text { Plant } & \mathrm { A } & \mathrm { B } & \mathrm { C } & \mathrm { D } \\ \hline 1 & 17 & 16 & 16 & 16 \\ 2 & 15 & 18 & 16 & 17 \\ 3 & 18 & 15 & 18 & 16 \\ \hline \end{array}      -Use the information in Table 9.7.What is the cost of a plan that ships 150 units from 1 to C,150 units from 1 to D,250 units from 2 to A,150 units from 2 to C,200 units from 3 to B,and 50 units from 3 to D? -Use the information in Table 9.7.What is the cost of a plan that ships 150 units from 1 to C,150 units from 1 to D,250 units from 2 to A,150 units from 2 to C,200 units from 3 to B,and 50 units from 3 to D?

(Multiple Choice)
4.7/5
(37)

Facility location is the process of determining a geographic site for a firm's operations.

(True/False)
4.9/5
(39)

Layout flexibility means either that the facility remains desirable after significant changes occur or that it can be easily and inexpensively adapted in response to changes.

(True/False)
4.8/5
(34)

Which one of the following statements is a disadvantage of a product layout?

(Multiple Choice)
4.8/5
(44)

Table 9.17 The Pennsylvania Appliance company is installing an assembly line to produce vacuum cleaners, and you, as an operations manager, are responsible for balancing the line. The work elements to be performed are listed, along with their items and immediate predecessors. Work Element Time (sec) Immediate Predecessor(s) 60 -- 40 30 20 40 60 70 50 , 20 60 , -Use the information in Table 9.17.What is the theoretical minimum number of stations (TM)for the line? If you are using the longest work-element time rule,how many workstations do you need?

(Multiple Choice)
4.7/5
(35)
Showing 101 - 120 of 217
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)