Exam 7: Lean Systems
Exam 1: Creating Customer Value through Operations128 Questions
Exam 2: Supply Chain Management171 Questions
Exam 3: Process Configuration137 Questions
Exam 4: Capacity145 Questions
Exam 5: Inventory Management177 Questions
Exam 6: Quality and Process Improvement240 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects153 Questions
Exam 9: Location and Layout217 Questions
Exam 10: Managing Demand and Forecasting189 Questions
Exam 11: Operations Planning and Scheduling138 Questions
Exam 12: Resource Planning174 Questions
Exam 13: Decision Making82 Questions
Exam 14: Financial Analysis41 Questions
Exam 15: Work Measurement98 Questions
Exam 16: Learning Curve Analysis44 Questions
Exam 17: Computer-Integrated Manufacturing53 Questions
Exam 18: Acceptance Sampling Plans71 Questions
Exam 19: Simulation36 Questions
Exam 20: Special Inventory Models33 Questions
Exam 21: Linear Programming57 Questions
Exam 22: Waiting Lines109 Questions
Select questions type
Table 7.2
A manufacturer using a kanban system has had problems with high inventory levels of one of the component parts it makes. Daily demand for the part is 3000 units, average waiting time during production is 0.20 day, processing time is 0.10 day per container, and a container holds 150 pieces.
-Use the information in Table 7.2.How many kanban containers would be required if a 5 % efficiency factor is used?
Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
C
List the inventory tactics appropriate for a JIT environment.
Free
(Essay)
4.7/5
(31)
Correct Answer:
Inventory tactics for a JIT environment include a pull system for ordering and moving inventory,ever smaller lots,just-in-time deliveries from suppliers,deliveries directly to point of use,performance to schedule,setup reduction,and group technology.
Table 7.3
A company uses a kanban system. The daily demand for part A is 4000 units. The average waiting time for a container of parts is 0.2 day. The processing time for a container of part A is 0.8 day, and a container holds 300 units.
-Use the information in Table 7.3.How many kanban containers would be required if a 15 % efficiency factor is used?
Free
(Multiple Choice)
4.9/5
(40)
Correct Answer:
D
Which of the following would not be a benefit of small production lots?
(Multiple Choice)
4.8/5
(26)
A company uses a kanban system.The daily demand for part A is 300 units.The average waiting time for a container of parts is 0.25 day.The processing time for a container of part A is 0.1 day,and a container holds 10 units.If the company wishes to use a 10% policy variable,how many containers are needed?
(Essay)
4.7/5
(43)
There are many requirements for the successful implementation of the JIT system of production.Which one of the following is not such a requirement of the JIT system?
(Multiple Choice)
4.8/5
(29)
A kanban system is an important mechanism for JIT management.Which one of the following statements regarding the operation of a kanban system is TRUE?
(Multiple Choice)
4.7/5
(29)
The push method of production is a method in which customer demand activates production of an item.
(True/False)
4.9/5
(37)
According to JIT,an approach to reduce product variation is
(Multiple Choice)
4.9/5
(35)
Is there a connection between lean production and social responsibility?
(Essay)
4.8/5
(46)
Generally describe some setup reduction ideas that a manufacturing company can apply.
(Essay)
4.8/5
(40)
Use of value stream mapping requires construction of a current state drawing,a future state drawing,and an implementation plan.
(True/False)
4.8/5
(31)
Showing 1 - 20 of 158