Exam 7: Integer Linear Programming
Exam 1: Introduction63 Questions
Exam 2: An Introduction to Linear Programming66 Questions
Exam 3: Linear Programming: Sensitivity Analysis and Interpretation of Solution56 Questions
Exam 4: Linear Programming Applications in Marketing, Finance, and Operations Management63 Questions
Exam 5: Advanced Linear Programming Applications46 Questions
Exam 6: Distribution and Network Models70 Questions
Exam 7: Integer Linear Programming61 Questions
Exam 8: Nonlinear Optimization Models51 Questions
Exam 9: Project Scheduling: Pertcpm59 Questions
Exam 10: Inventory Models65 Questions
Exam 11: Waiting Line Models68 Questions
Exam 12: Simulation62 Questions
Exam 13: Decision Analysis97 Questions
Exam 14: Multicriteria Decisions50 Questions
Exam 15: Time Series Analysis and Forecasting63 Questions
Exam 16: Markov Processes49 Questions
Exam 17: Linear Programming: Simplex Method51 Questions
Exam 18: Simplex-Based Sensitivity Analysis and Duality35 Questions
Exam 19: Solution Procedures for Transportation and Assignment Problems44 Questions
Exam 20: Minimal Spanning Tree19 Questions
Exam 21: Dynamic Programming38 Questions
Select questions type
Tower Engineering Corporation is considering undertaking several proposed projects for the next fiscal year. The projects, the number of engineers and the number of support personnel required for each project, and the expected profits for each project are summarized in the following table:
Formulate an integer program that maximizes Tower's profit subject to the following management constraints:
1)
Use no more than 175 engineers
2)
Use no more than 150 support personnel
3)
If either project 6 or project 4 is done, both must be done
4)
Project 2 can be done only if project 1 is done
5)
If project 5 is done, project 3 must not be done and vice versa
6)
No more than three projects are to be done.