Exam 9: Reducing Project Duration
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
The accuracy of crash times and costs is frequently rough at best, when compared with normal time and cost.
(True/False)
4.8/5
(31)
What if cost, not time, is the issue? What are some options available to project managers? Identify and briefly describe three.
(Essay)
4.8/5
(33)
When considering whether to move the project to its optimum cost-time position, the manager should also consider ________.
(Multiple Choice)
4.8/5
(40)
When adding resources, there are limits as to how much speed can be gained.
(True/False)
4.9/5
(40)
An activity's normal time and cost are 10 and $120, respectively. Its estimated crash time and cost are 7 and $180, respectively. What is this activity's crash cost per time unit?
(Multiple Choice)
4.9/5
(42)
When the project team is salaried, which of the following is the preferred choice for accelerating project completion?
(Multiple Choice)
4.9/5
(37)
Consider the following table of activities that describes a project network. Which activity will you crash second?
(Multiple Choice)
4.9/5
(38)
Brooks' law states that adding manpower to a software project helps keep it on schedule.
(True/False)
4.8/5
(38)
Which of the following is NOT a rational reason to reduce project duration?
(Multiple Choice)
4.7/5
(38)
Creation of the ___________ graph keeps the importance of indirect costs in the forefront of decision making.
(Multiple Choice)
4.8/5
(34)
When crashing a schedule, this may set in when a least-cost method is used.
(Multiple Choice)
4.7/5
(34)
As a project's duration is reduced, indirect costs are ___________.
(Multiple Choice)
4.9/5
(31)
The cost-time crashing method relies on choosing the cheapest method for reducing the duration of the project. What are other factors that should be assessed beyond simply cost?
(Essay)
5.0/5
(28)
The ________ time for an activity represents low-cost, realistic, efficient methods for completing the activity under typical conditions.
(Multiple Choice)
4.8/5
(40)
There are more options available for reducing project time if you are not resource constrained.
(True/False)
4.9/5
(39)
In a Project Cost-Duration Graph, total project costs are a sum of
(Multiple Choice)
4.8/5
(27)
_________ is the first thing to consider when deciding whether or not an activity can be crashed.
(Multiple Choice)
4.8/5
(41)
As a project is crashed and project duration is reduced, direct costs typically
(Multiple Choice)
4.8/5
(38)
The ________ project cost is the sum of the indirect and direct costs.
(Multiple Choice)
4.7/5
(45)
Showing 41 - 60 of 106
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)