Exam 9: Reducing Project Duration

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Before crashing, direct costs for an activity represent normal costs, which typically mean low-cost, efficient methods for completing the activity in a(n) ________ amount of time.

(Multiple Choice)
4.8/5
(40)

Crashing can negatively impact the morale and motivation of the project team.

(True/False)
4.7/5
(32)

Crashing frequently results in over allocation of resources.

(True/False)
4.8/5
(36)

For most projects, the estimation of a crash time is relatively easy.

(True/False)
4.8/5
(43)

____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.

(Multiple Choice)
4.8/5
(39)

It is going to cost $120,000 a day simply to house and feed a construction crew in the farthest reaches of northern Alaska. This would be an example of a situation requiring reducing the project duration due to

(Multiple Choice)
4.9/5
(40)

When crashing an activity, you always crash to its crash point.

(True/False)
4.9/5
(39)

When determining which activity to crash, there are other factors that should be assessed beyond cost. Which of the following is NOT one of these factors?

(Multiple Choice)
4.9/5
(42)

Resources are frequently over-allocated when crashing a schedule.

(True/False)
4.9/5
(44)

According to Brooks' Law, adding more people to a late project is most likely to have which of the following impacts?

(Multiple Choice)
4.9/5
(40)

The cost slope of an activity is calculated by dividing the run by the rise.

(True/False)
4.8/5
(38)

Given an equal level of risk and the need to reduce overall project duration, why would you NOT select the activity with the least slope, in the entire project network, to crash first?

(Essay)
4.9/5
(41)

Which of the following is NOT considered a project indirect cost?

(Multiple Choice)
4.9/5
(24)

As a project is crashed and project duration is reduced, indirect costs typically

(Multiple Choice)
4.8/5
(37)

Shortening an activity's duration is termed crashing.

(True/False)
4.9/5
(31)

Direct costs are so named because they can be assigned directly to a work package and activity.

(True/False)
5.0/5
(47)

Reducing the duration of an activity is called ________.

(Multiple Choice)
4.8/5
(37)

Why should a project manager be cautious when adding resources to reduce project duration?

(Essay)
4.8/5
(30)

A construction contractor finished a bridge across a river 12 months early and received more than $5 million for the early completion. This is an example of reducing project duration caused by

(Multiple Choice)
4.8/5
(36)

When reducing project duration, there will always be an optimum cost-time point where the total cost of the project is less than it was when the project was initially planned under normal conditions.

(True/False)
4.9/5
(37)
Showing 21 - 40 of 106
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)