Exam 15: Key Concepts in Construction Management and Delivery Methods

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

Learning curve and work schedule studies would be used in estimating the???? of an estimate.

(Multiple Choice)
4.9/5
(42)

Match the letter in the project control chart shown in the figure with the corresponding item in the following. Match the letter in the project control chart shown in the figure with the corresponding item in the following.    -External factors -External factors

(Short Answer)
4.9/5
(40)

One advantage of the design/build approach is that usually a firm project cost is established before construction begins.

(True/False)
4.8/5
(31)

Match the description with the terms listed.Terms may be used only once. -Defines conditions applicable to all contracts awarded

(Multiple Choice)
4.9/5
(33)

Match the type of schedule listed with the description following. Schedule types may be used more than once. -Would be used for a summary report to the owner

(Multiple Choice)
4.8/5
(40)

Match the type of schedule listed with the description following. Schedule types may be used more than once. -Could also be termed precedent notation

(Multiple Choice)
4.8/5
(35)

The developer of a 40-story high-rise office building desires the shortest possible construction time. What contractual arrangement would be best?

(Multiple Choice)
4.8/5
(37)

Construction managers are usually hired in a professional capacity, as are architects and engineers.

(True/False)
4.9/5
(40)

Identify the person responsible for the following aspects of a project. -Drawings and specifications

(Multiple Choice)
4.8/5
(39)

Cost codes are used for which of the following reasons?

(Multiple Choice)
5.0/5
(35)

In a Design/Bid/Build arrangement, a (an) ????contract is most likely used between a general contractor and an owner.

(Multiple Choice)
4.8/5
(32)

If an owner has only a fixed amount to spend and would not build a project if its cost would exceed this amount, construction management would be the preferred delivery method.

(True/False)
4.8/5
(39)

Unlike the high-technology industry, the construction industry does not place much emphasis on R & D.

(True/False)
4.9/5
(32)

Match the description with the terms listed.Terms may be used only once. -Tracks submittals

(Multiple Choice)
4.8/5
(31)

When compared to other delivery method options, which of the following is not considered an advantage of Design/Bid/Build delivery?

(Multiple Choice)
4.7/5
(31)

Traditionally, concept and feasibility studies are handled by the????

(Multiple Choice)
4.9/5
(42)

The ????section of a bid package defines the technical requirements, scope, and quality of the project.

(Multiple Choice)
4.8/5
(38)

Which conclusion is correct based on the following figure? Which conclusion is correct based on the following figure?

(Multiple Choice)
4.9/5
(38)

Identify in which listed project phase each following project activity would normally occur. Use each phase once only. -Approve trade contractor progress payments

(Multiple Choice)
4.8/5
(37)

Construction management is superior to Design/Bid/Build approaches at addressing which of the following concerns?

(Multiple Choice)
4.9/5
(36)
Showing 81 - 100 of 135
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)