Exam 16: Job and Staff Scheduling
Exam 1: Introduction to Operations Management63 Questions
Exam 2: Competitiveness, Strategic Planning, and Productivity54 Questions
Exam 3: Demand Forecasting172 Questions
Exam 4: A: Product Design74 Questions
Exam 4: B: Product Design56 Questions
Exam 5: A: Strategic Capacity Planning74 Questions
Exam 5: B: Strategic Capacity Planning64 Questions
Exam 6: A: Process Design and Facility Layout157 Questions
Exam 6: B: Process Design and Facility Layout99 Questions
Exam 7: A: Design of Work Systems143 Questions
Exam 7: B: Design of Work Systems68 Questions
Exam 8: A: Location Planning and Analysis74 Questions
Exam 8: B: Location Planning and Analysis16 Questions
Exam 9: Management of Quality98 Questions
Exam 10: A: Statistical Quality Control121 Questions
Exam 10: B: Statistical Quality Control61 Questions
Exam 11: Supply Chain Management86 Questions
Exam 12: Inventory Management168 Questions
Exam 13: Aggregate Operations Planning71 Questions
Exam 14: Material Requirements Planning and Enterprise Resource Planning84 Questions
Exam 15: A: Just-In-Time and Lean Production82 Questions
Exam 15: B: Just-In-Time and Lean Production32 Questions
Exam 16: Job and Staff Scheduling112 Questions
Exam 17: Project Management127 Questions
Exam 18: A: Waiting-Line Analysis76 Questions
Exam 18: B: Waiting-Line Analysis41 Questions
Select questions type
If Jack uses the earliest due date first (EDD)priority rule to schedule these jobs,what will be the average job lateness?
Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
B
If Jack uses the shortest processing time first (SPT)priority rule to schedule these jobs,what will be the average job lateness?
Free
(Multiple Choice)
4.7/5
(38)
Correct Answer:
A
Finite loading does not account for the capacity of work centres.
Free
(True/False)
4.8/5
(37)
Correct Answer:
False
In scheduling staff for services,flexible capacity is achieved by:
(Multiple Choice)
4.7/5
(30)
Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by Machine B:
-In developing the sequence that will minimize make-span,where in the schedule sequence should the job W be placed?

(Short Answer)
4.8/5
(31)
If Jack uses the shortest processing time first (SPT)priority rule to schedule these jobs,what will be the average WIP in his shop today?
(Multiple Choice)
4.7/5
(36)
For the Theory of Constraints,the transfer batch denotes a portion of the production lot that could be moved to the bottleneck operation.
(True/False)
4.9/5
(40)
Using the information below,determine the following:
(i)processing sequence using (1)SPT and (2)EDD and (3)MST rules
(ii)average flow time and average job lateness under each rule


(Essay)
4.8/5
(30)
The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival):
-What is the average flow time for the minimum slack time (MST)priority rule schedule (using the CR rule to break ties)?
Average job lateness?
Average WIP at the centre?



(Short Answer)
4.7/5
(37)
A Gantt chart is a visual aid for loading,scheduling,and control purposes.
(True/False)
4.8/5
(29)
The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival):
-What is the average flow time for the earliest due date (EDD)priority rule schedule?
Average job lateness?
Average WIP at the centre?

(Short Answer)
4.9/5
(36)
A major reason for scheduling difficulty is variability in setup times,processing times,interruptions,and changes in the set of jobs.
(True/False)
4.9/5
(36)
Given the following information concerning jobs awaiting processing at a single work centre,what is the processing sequence using the critical ratio (CR)rule?


(Essay)
4.8/5
(28)
Given the information below,determine the following:
(i)Processing sequence using (1)SPT and (2)EDD.
(ii)Average flow time and average job lateness using (1)SPT and (2)EDD.


(Essay)
4.9/5
(28)
Using Johnson's rule what is the optimum sequence (first car to last)?
(Multiple Choice)
4.8/5
(25)
For services,the process of assigning work shifts to staff begins with forecasting the amount of work to be done during each hour (or shift)during the time period the schedule is being planned.
(True/False)
4.9/5
(32)
Which sequencing rule is designed specifically to minimize job lateness?
(Multiple Choice)
4.7/5
(31)
If he uses the shortest processing time first (SPT)priority rule to schedule these jobs,what will be the average WIP in his shop today?
(Multiple Choice)
4.9/5
(34)
Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by Machine B:
-In developing the sequence which will minimize throughput time,where should the job X be placed?

(Short Answer)
4.9/5
(31)
The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival):
-What is the schedule sequence using the earliest due date (EDD)priority rule?

(Short Answer)