Exam 16: Job and Staff Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

If Jack uses the earliest due date first (EDD)priority rule to schedule these jobs,what will be the average job lateness?

Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
Verified

B

If Jack uses the shortest processing time first (SPT)priority rule to schedule these jobs,what will be the average job lateness?

Free
(Multiple Choice)
4.7/5
(38)
Correct Answer:
Verified

A

Finite loading does not account for the capacity of work centres.

Free
(True/False)
4.8/5
(37)
Correct Answer:
Verified

False

In scheduling staff for services,flexible capacity is achieved by:

(Multiple Choice)
4.7/5
(30)

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by Machine B: Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by Machine B:    -In developing the sequence that will minimize make-span,where in the schedule sequence should the job W be placed? -In developing the sequence that will minimize make-span,where in the schedule sequence should the job W be placed?

(Short Answer)
4.8/5
(31)

If Jack uses the shortest processing time first (SPT)priority rule to schedule these jobs,what will be the average WIP in his shop today?

(Multiple Choice)
4.7/5
(36)

For the Theory of Constraints,the transfer batch denotes a portion of the production lot that could be moved to the bottleneck operation.

(True/False)
4.9/5
(40)

Using the information below,determine the following: (i)processing sequence using (1)SPT and (2)EDD and (3)MST rules (ii)average flow time and average job lateness under each rule Using the information below,determine the following: (i)processing sequence using (1)SPT and (2)EDD and (3)MST rules (ii)average flow time and average job lateness under each rule

(Essay)
4.8/5
(30)

The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival): The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival):    -What is the average flow time for the minimum slack time (MST)priority rule schedule (using the CR rule to break ties)?  Average job lateness?  Average WIP at the centre?   -What is the average flow time for the minimum slack time (MST)priority rule schedule (using the CR rule to break ties)? Average job lateness? Average WIP at the centre? The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival):    -What is the average flow time for the minimum slack time (MST)priority rule schedule (using the CR rule to break ties)?  Average job lateness?  Average WIP at the centre?

(Short Answer)
4.7/5
(37)

A Gantt chart is a visual aid for loading,scheduling,and control purposes.

(True/False)
4.8/5
(29)

The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival): The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival):    -What is the average flow time for the earliest due date (EDD)priority rule schedule?  Average job lateness?  Average WIP at the centre? -What is the average flow time for the earliest due date (EDD)priority rule schedule? Average job lateness? Average WIP at the centre?

(Short Answer)
4.9/5
(36)

A major reason for scheduling difficulty is variability in setup times,processing times,interruptions,and changes in the set of jobs.

(True/False)
4.9/5
(36)

Given the following information concerning jobs awaiting processing at a single work centre,what is the processing sequence using the critical ratio (CR)rule? Given the following information concerning jobs awaiting processing at a single work centre,what is the processing sequence using the critical ratio (CR)rule?

(Essay)
4.8/5
(28)

Given the information below,determine the following: (i)Processing sequence using (1)SPT and (2)EDD. (ii)Average flow time and average job lateness using (1)SPT and (2)EDD. Given the information below,determine the following: (i)Processing sequence using (1)SPT and (2)EDD. (ii)Average flow time and average job lateness using (1)SPT and (2)EDD.

(Essay)
4.9/5
(28)

Using Johnson's rule what is the optimum sequence (first car to last)?

(Multiple Choice)
4.8/5
(25)

For services,the process of assigning work shifts to staff begins with forecasting the amount of work to be done during each hour (or shift)during the time period the schedule is being planned.

(True/False)
4.9/5
(32)

Which sequencing rule is designed specifically to minimize job lateness?

(Multiple Choice)
4.7/5
(31)

If he uses the shortest processing time first (SPT)priority rule to schedule these jobs,what will be the average WIP in his shop today?

(Multiple Choice)
4.9/5
(34)

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by Machine B: Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by Machine B:    -In developing the sequence which will minimize throughput time,where should the job X be placed? -In developing the sequence which will minimize throughput time,where should the job X be placed?

(Short Answer)
4.9/5
(31)

The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival): The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival):    -What is the schedule sequence using the earliest due date (EDD)priority rule? -What is the schedule sequence using the earliest due date (EDD)priority rule?

(Short Answer)
4.7/5
(34)
Showing 1 - 20 of 112
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)