The ________ rule assumes credit is earned for having performed the work once it is completed.This rule is usually used for work packages having very short durations.

(Short Answer)
4.9/5
(37)

Schedule variance (SV)is in dollars and does not directly represent time.Why is it still useful?

(Not Answered)
This question doesn't have any answer yet
Ask our community

All projects need some form of formal control.Agree or disagree? Support you answer.

(Not Answered)
This question doesn't have any answer yet
Ask our community

The cost variance for a project is calculated by

(Multiple Choice)
4.9/5
(34)

A project manager learns that the project is only earning $.90 of planned work for each dollar spent by looking at the

(Multiple Choice)
4.8/5
(37)

When revising the estimated cost at completion,there are two approaches.The EACre is determined by experts in the field and the EACf is a mathematical approach which assumes the CPI as the basis for forecasting cost at completion.

(True/False)
4.8/5
(31)

________ is simply the percent complete times the original budget.

(Short Answer)
4.8/5
(31)

Schedule variance measures progress in time units.

(True/False)
4.8/5
(29)