Exam 13: Progress and Performance Measurement and Evaluation
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
Although it is very difficult to measure, measuring technical performance is as important as measuring schedule and cost performance.
(True/False)
4.8/5
(31)
Because of their easy-to-understand visual format, ________ charts are the most favored, used, and understandable tool used to report project schedule status.
(Short Answer)
4.7/5
(37)
A ___________ Gantt chart is a simple and effective way to depict progress on a project.
(Multiple Choice)
4.7/5
(34)
A negative Cost Variance combined with a negative Schedule Variance is an indicator of
(Multiple Choice)
4.9/5
(31)
The Schedule Variance is the best way to get an accurate assessment of schedule performance.
(True/False)
4.7/5
(29)
What is the difference between a baseline Gantt chart and a tracking Gantt chart?
(Essay)
4.9/5
(35)
Which of the following methods will measure the scheduling efficiency of the work accomplished to date?
(Multiple Choice)
4.9/5
(33)
Which of the following methods will measure the cost efficiency of the work accomplished to date?
(Multiple Choice)
4.7/5
(31)
The value that tells you the planned value of the actual work completed is ___________.
(Short Answer)
4.8/5
(40)
Two project complete indexes are used, depending on your judgment of which one is most representative of your project.Identify both indexes and explain when it is most appropriate to use each.
(Essay)
4.8/5
(35)
The first step in creating a project control system for measuring and evaluating project performance is to set a ________.
(Short Answer)
4.7/5
(25)
Conducting an earned value analysis requires three data elements.Identify the acronyms for each and describe what they are.
(Essay)
4.9/5
(32)
A project monitoring system involves all of the following EXCEPT
(Multiple Choice)
4.9/5
(36)
A scope change is always viewed negatively as it changes the delivery date of the project.
(True/False)
4.8/5
(34)
The PV, AC and CV are all required to assess the current status of the project.
(True/False)
4.8/5
(39)
When reviewing the variance on a project, you compare Earned Value with
(Multiple Choice)
4.7/5
(32)
The second step in the project control process for measuring and evaluating project performance is to
(Multiple Choice)
4.9/5
(38)
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the
(Multiple Choice)
4.8/5
(33)
A project can have a negative Schedule Variance and still be ahead of schedule when
A.All budget targets have been achieved.
B.Non-Critical task delays are greater than progress on the Critical Path.
C.Progress on the Critical Path is faster than non-critical path tasks.
D.None of these choices are correct.
(Essay)
4.9/5
(35)
Which performance index is the most potentially misleading?
(Multiple Choice)
4.9/5
(36)
Showing 61 - 80 of 101
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)