Exam 13: Progress and Performance Measurement and Evaluation
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
The final step in the project control process for measuring and evaluating project performance is to
(Multiple Choice)
4.8/5
(43)
The ________ rule assumes credit is earned for having performed the work once it is completed.This rule is usually used for work packages having very short durations.
(Short Answer)
4.9/5
(37)
The ratio that measures the amount of value each remaining dollar in the budget must earn to stay within the budget is the _________.
(Short Answer)
4.8/5
(42)
A tool used to monitor past project schedule performance and current performance, and to estimate future schedule trends is a simple line chart known as a
(Multiple Choice)
4.9/5
(36)
A negative VAC indicates that the project will be completed over budget.
(True/False)
4.7/5
(30)
Baseline costs typically include labor, equipment, materials and direct overhead cost.
(True/False)
4.9/5
(45)
Identify the steps in creating a control process that measures and evaluates project performance.
(Essay)
5.0/5
(38)
Given a BAC of 5,500 and an EAC of 6,000, the project is expected to be completed _________ budget.
(Short Answer)
4.8/5
(31)
The project network schedule is derived from the _______ and it serves as the baseline to compare against actual performance.
(Short Answer)
4.8/5
(37)
An undesirable schedule variance always indicates that the project is running behind schedule.
(True/False)
4.7/5
(21)
The value that tells you the planned value of work that has actually been completed is the
(Multiple Choice)
4.9/5
(29)
A "rubber baseline" occurs when, in an effort to disguise poor performance, the baseline changes to constantly match results.
(True/False)
4.8/5
(26)
In reviewing the budget report of a project, you notice that spending on the project is running about 10 percent over plan.Is the project in trouble? Why or why not?
(Essay)
4.9/5
(30)
What is a "rubber baseline" and how does it undermine project control?
(Essay)
4.8/5
(29)
A project manager learns that the project is only earning $.90 of planned work for each dollar spent by looking at the
(Multiple Choice)
4.8/5
(34)
The third step in the project control process for measuring and evaluating project performance is to
(Multiple Choice)
4.8/5
(35)
Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500, EAC = 1208.In terms of cost at completion.
(Multiple Choice)
4.9/5
(34)
Progress and performance can be measured quantitatively as well as qualitatively.
(True/False)
4.7/5
(33)
All scope changes that result in increased costs should be avoided.
(True/False)
4.9/5
(31)
Showing 21 - 40 of 101
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)