Exam 13: Progress and Performance Measurement and Evaluation
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
The first step in the project control process for measuring and evaluating project performance is to
(Multiple Choice)
4.9/5
(45)
Schedule variance (SV)is in dollars and does not directly represent time.Why is it still useful?
(Essay)
4.8/5
(32)
The start of a task may be moved on a Tracking Gantt due to
(Multiple Choice)
4.8/5
(36)
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the ____________ rule.
(Short Answer)
4.7/5
(37)
If the cost of labor and materials has not been separated there is additional analysis required to determine the cause of the calculated variance.
(True/False)
4.9/5
(43)
A common project practice is to ignore straight labor hours when calculating Earned Value.
(True/False)
4.8/5
(34)
The _________ index measures the project percent complete in relation to the resources that were budgeted.
(Short Answer)
4.9/5
(35)
What is the percent complete rule and what role does it play when developing an earned value cost/schedule system?
(Essay)
4.7/5
(34)
Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?
(Multiple Choice)
4.9/5
(36)
Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work.Nancy got this information from viewing the
(Multiple Choice)
4.7/5
(29)
Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?
(Multiple Choice)
4.7/5
(40)
When revising the estimated cost at completion, there are two approaches.The EACre is determined by experts in the field and the EACf is a mathematical approach which assumes the CPI as the basis for forecasting cost at completion.
(True/False)
4.8/5
(41)
Most changes will not result in serious scope changes and should be absorbed as positive or negative variances.
(True/False)
4.9/5
(36)
Sally receives the following information on her project: PV = 100, AC = 75, EV = 100.How well is the project doing in terms of budget?
(Multiple Choice)
4.7/5
(37)
Deciding what data to collect, actually collecting the data and analyzing it, and reporting this data are all parts of structuring a project monitoring information system.
(True/False)
4.8/5
(40)
All projects need some form of formal control.Agree or disagree? Support you answer.
(Essay)
4.7/5
(38)
A project control system allows for comparing actual performance against plan to identify deviations; however, the system doesn't impact the quality of communication between stakeholders.
(True/False)
4.9/5
(42)
Showing 81 - 100 of 101
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)