The first step in the project control process for measuring and evaluating project performance is to

(Multiple Choice)
4.9/5
(45)

Schedule variance (SV)is in dollars and does not directly represent time.Why is it still useful?

(Essay)
4.8/5
(32)

What is scope creep and how does it impact project control?

(Essay)
4.9/5
(41)

The start of a task may be moved on a Tracking Gantt due to

(Multiple Choice)
4.8/5
(36)

When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the ____________ rule.

(Short Answer)
4.7/5
(37)

If the cost of labor and materials has not been separated there is additional analysis required to determine the cause of the calculated variance.

(True/False)
4.9/5
(43)

A common project practice is to ignore straight labor hours when calculating Earned Value.

(True/False)
4.8/5
(34)

The _________ index measures the project percent complete in relation to the resources that were budgeted.

(Short Answer)
4.9/5
(35)

What is the percent complete rule and what role does it play when developing an earned value cost/schedule system?

(Essay)
4.7/5
(34)

The schedule variance for a project is calculated by:

(Multiple Choice)
4.9/5
(35)

Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?

(Multiple Choice)
4.9/5
(36)

Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work.Nancy got this information from viewing the

(Multiple Choice)
4.7/5
(29)

Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?

(Multiple Choice)
4.7/5
(40)

When revising the estimated cost at completion, there are two approaches.The EACre is determined by experts in the field and the EACf is a mathematical approach which assumes the CPI as the basis for forecasting cost at completion.

(True/False)
4.8/5
(41)

Most changes will not result in serious scope changes and should be absorbed as positive or negative variances.

(True/False)
4.9/5
(36)

Sally receives the following information on her project: PV = 100, AC = 75, EV = 100.How well is the project doing in terms of budget?

(Multiple Choice)
4.7/5
(37)

Deciding what data to collect, actually collecting the data and analyzing it, and reporting this data are all parts of structuring a project monitoring information system.

(True/False)
4.8/5
(40)

All projects need some form of formal control.Agree or disagree? Support you answer.

(Essay)
4.7/5
(38)

A project control system allows for comparing actual performance against plan to identify deviations; however, the system doesn't impact the quality of communication between stakeholders.

(True/False)
4.9/5
(42)

Schedule variance measures progress in time units.