Exam 13: Progress and Performance Measurement and Evaluation
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
Rachel notices that the current EV for her project is higher than both the PV and the AC.Rachel has reason to be concerned.
(True/False)
4.9/5
(36)
The indicator that tells you the amount each remaining dollar must earn in order for the project to stay within budget is the
(Multiple Choice)
4.9/5
(38)
________ holds people accountable, prevents small problems from mushrooming into large problems, and keeps focus.
(Short Answer)
4.8/5
(30)
Identify and describe two methods for tracking and trending schedule performance.
(Essay)
4.8/5
(38)
Earned value is defined as the budgeted cost of the actual work performed.
(True/False)
4.9/5
(38)
The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.
(Short Answer)
4.9/5
(37)
Given that the AC = 300, PV = 400 and EV = 500, this project is _________ budget.
(Short Answer)
4.8/5
(36)
Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333.How is the project doing in terms of schedule?
(Multiple Choice)
4.9/5
(35)
A project manager notices that $1,000 worth of work that was scheduled to be completed at this time has not been accomplished.They know this by looking at the
(Multiple Choice)
4.8/5
(34)
The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time.
(True/False)
4.8/5
(34)
The best method for assigning costs to the baseline under the 50/50 rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms.
(True/False)
4.8/5
(38)
A Cost/Schedule graph can be interpreted using ___________ and __________ for its axis.
(Multiple Choice)
4.8/5
(35)
The earned value system starts with the time-phased costs that provide the project baseline, which is called the
(Multiple Choice)
4.8/5
(36)
In calculating schedule variance and cost variance, a negative variance indicates a desirable condition, and a positive variance suggests problems.
(True/False)
4.8/5
(38)
The baseline is derived from merging information from the work packages with the project network.
(True/False)
4.9/5
(25)
A project manager learns that her project has an EV of 1200, AC of 1100 and PV of 1000.What can the project manager report regarding this project?
(Essay)
4.9/5
(31)
The final step in the project control process for measuring and evaluating project performance is to take appropriate ________.