Unavoidable delays should not be included in time studies.

Free
(True/False)
4.9/5
(40)
Correct Answer:
Verified

False

A 90% learning curve implies faster learning than an 80% learning curve.

Free
(True/False)
4.9/5
(39)
Correct Answer:
Verified

False

The learning curve does not apply to supervisory personnel, some skilled craftspeople or jobs that have non-repetitive job tasks.

Free
(True/False)
4.8/5
(36)
Correct Answer:
Verified

True

For a time study, it is assumed the distribution of task times follow a Poisson distribution.

(True/False)
4.9/5
(41)

Regression analysis is used to predict times based on different attributes of work.

(True/False)
4.7/5
(23)

The performance rating factor and allowances are based upon human judgment.

(True/False)
4.8/5
(38)

Consider the work sampling information below. Consider the work sampling information below.    a.If the performance rating factor for Q = 0.80, R = 1.10 and S = 1.10 and the total allowance is 17%, determine the normal time for the job. b.With the allowance of 17%, determine the output per hour. a.If the performance rating factor for Q = 0.80, R = 1.10 and S = 1.10 and the total allowance is 17%, determine the normal time for the job. b.With the allowance of 17%, determine the output per hour.

(Essay)
4.8/5
(32)

A yacht manufacturer signed a contract to build five sailboats for a California resort.Assuming an 85% learning curve, how many labor-hours will it take to build all five sailboats if it took 7,000 standard hours to build the original sailboat?

(Essay)
4.9/5
(32)

A furniture manufacturer has an order for 20 custom wine cabinets for a large hotel in Hawaii.It is estimated that the first cabinet will take 100 hours of shop time.An 85% learning curve is expected.The labor rate is $12.00 per hour.The pricing policy is to charge two times the labor cost for the order. a.How many hours will the 20th wine cabinet take? b.How many hours should the whole order take? c.What is the price of each cabinet?

(Essay)
4.8/5
(33)

A manufacturer made a commitment to supply 20 units of a product.The first unit took 1,200 hours to make, the second unit took 900 hours and the third unit took 768 hours.Determine the total number of hours required to make the first ten (10) items.

(Essay)
4.8/5
(30)

At an 80% learning rate, if the first unit requires 100 labor hours, the 8th unit will require 64 hours.

(True/False)
4.8/5
(37)

Which is not a practical issue when using learning curves?

(Multiple Choice)
4.8/5
(36)

Consider the following time study data. Consider the following time study data.   a.If the performance rating factor for A = 1.15, B = 1.0 and C = 0.85, determine the normal time for the job. b.If personal allowance is 7%, fatigue allowance is 12%, personal delay allowance is 9% and avoidable delay is 4 minutes, determine the standard time for the job. a.If the performance rating factor for A = 1.15, B = 1.0 and C = 0.85, determine the normal time for the job. b.If personal allowance is 7%, fatigue allowance is 12%, personal delay allowance is 9% and avoidable delay is 4 minutes, determine the standard time for the job.

(Essay)
4.8/5
(40)

A method of randomly observing work over a period of time to obtain a distribution of the activities that an individual or a group of employees performs is called

(Multiple Choice)
4.8/5
(39)

A Performance Rating Factor (PRF) of 130% means a worker is slow and needs 30% more time.

(True/False)
4.9/5
(37)

Predetermined time standards are advantageous since they avoid needing multiple performance ratings.

(True/False)
4.8/5
(38)

The outputs from a work measurement study leads to development of labor and equipment standards that are used for all of the following except

(Multiple Choice)
4.9/5
(32)

A job had a normal time of 2.43 minutes, an allowance of 20% and a forecast demand of 120 units per day.How long should it take to produce one day's output?

(Essay)
4.9/5
(29)

Predetermined time standards are

(Multiple Choice)
4.8/5
(37)

When timing a work activity with multiple tasks, the general rule is to take the largest sample size estimate and use it for all activities or tasks.

(True/False)
4.9/5
(36)