Exam 15: Resource Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Information concerning on-hand quantities,lot sizes and,lead time,figures can be found in the master production schedule (MPS).

Free
(True/False)
4.9/5
(34)
Correct Answer:
Verified

False

The item master file contains all the following except

Free
(Multiple Choice)
4.8/5
(42)
Correct Answer:
Verified

C

Material requirements planning (MRP)is a useful for all of the following except

Free
(Multiple Choice)
4.9/5
(41)
Correct Answer:
Verified

C

Given the following MRP matrix for Item C: Given the following MRP matrix for Item C:   If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Planned Order Release for period 1 would be If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Planned Order Release for period 1 would be

(Multiple Choice)
4.7/5
(33)

A load profile displays underloads and overloads.

(True/False)
4.8/5
(30)

How does MRP differ from traditional inventory control systems?

(Essay)
4.8/5
(34)

Given the following Product Structure Record Given the following Product Structure Record   The number of I's required for each A would be The number of I's required for each A would be

(Multiple Choice)
4.8/5
(31)

Material requirements planning (MRP)is more useful for simple products and less useful for complex products.

(True/False)
4.9/5
(26)

A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period. A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period.   If EOQ lot sizing is used to set the minimum order quantity,then the projected on hand quantity at the end of period 3 would be If EOQ lot sizing is used to set the minimum order quantity,then the projected on hand quantity at the end of period 3 would be

(Multiple Choice)
4.8/5
(34)

A forecast of dependent demand requirements is one of the major inputs into the MRP process.

(True/False)
4.9/5
(34)

Very simple products typically do not require material requirements planning (MRP)to plan production or monitor inventory levels.

(True/False)
4.9/5
(34)

Given the following MRP matrix for Item E: Given the following MRP matrix for Item E:   The planned order releases for period 1 would be The planned order releases for period 1 would be

(Multiple Choice)
4.8/5
(33)

The MRP process of determining requirements for lower level items based on the master production schedule is referred to as

(Multiple Choice)
4.8/5
(29)

Given the following MRP matrix for Item C: Given the following MRP matrix for Item C:   If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Projected on Hand at the end of period 7 would be If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Projected on Hand at the end of period 7 would be

(Multiple Choice)
4.9/5
(44)

The MRP process of subtracting on-hand quantities and scheduled receipts from gross requirements to produce net requirements is referred to as

(Multiple Choice)
4.8/5
(37)

Given the following MRP matrix for Item D: Given the following MRP matrix for Item D:   The planned order release for period 5 would be The planned order release for period 5 would be

(Multiple Choice)
4.8/5
(40)

Customer relationship management systems change the focus from managing products to managing customers.

(True/False)
4.7/5
(42)

A _______________ of material is used to plan the production of products with many optional features.

(Multiple Choice)
4.9/5
(31)

Which of the following would not be used for an overloaded condition?

(Multiple Choice)
4.8/5
(31)

Given the following Product Structure Record Given the following Product Structure Record   The number of G's required to assemble 10 A's would be The number of G's required to assemble 10 A's would be

(Multiple Choice)
4.8/5
(28)