Exam 9: Project Management
Exam 1: Operations Management63 Questions
Exam 2: Quality Management71 Questions
Exam 3: Statistical Quality Control111 Questions
Exam 4: Product Design75 Questions
Exam 5: Service Design79 Questions
Exam 6: Processes and Technology61 Questions
Exam 17: Scheduling80 Questions
Exam 7: Capacity and Facilities83 Questions
Exam 8: Human Resources79 Questions
Exam 9: Project Management85 Questions
Exam 10: Supply Chain Management: Strategy and Design56 Questions
Exam 11: Global Supply Chain Procurement and Distribution69 Questions
Exam 12: Forecasting85 Questions
Exam 13: Inventory Management78 Questions
Exam 13: Operational Decision-Making Tools: Simulation22 Questions
Exam 14: Operational Decision-Making Tools: Linear Programming29 Questions
Exam 14: The Sales and Operations Planning Process76 Questions
Exam 15: Resource Planning82 Questions
Exam 16: Lean Systems79 Questions
Exam 18: Operational Decision-Making Tools: Decision Analysis38 Questions
Exam 19: Operational Decision-Making Tools: Acceptance Sampling28 Questions
Exam 20: Decision-Making Tools: Facility Location Models23 Questions
Exam 21: Operational Decision-Making Tools: Work Measurement31 Questions
Select questions type
A project consists of the following activities:
Table 9.1
-Using Table 9.1,the time complete the entire project is

Free
(Multiple Choice)
4.7/5
(31)
Correct Answer:
B
Because the critical path is the shortest path through a network it defines the minimum project completion time.
Free
(True/False)
4.8/5
(29)
Correct Answer:
False
PERT stands for program enterprise and resource technique.
Free
(True/False)
4.8/5
(21)
Correct Answer:
False
The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the earliest finish time for activity C is

(Multiple Choice)
4.7/5
(35)
The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the variance of the project's total completion time is

(Multiple Choice)
4.9/5
(33)
Which of the following is not a general characteristic of a project?
(Multiple Choice)
4.8/5
(49)
Global projects rarely are concerned with cultural differences among team members because English is the universal business language.
(True/False)
5.0/5
(41)
Indirect costs always increase as a project's duration decreases.
(True/False)
4.9/5
(28)
A project consists of the following four activities with activity times in days:
Table 9.3
-Using Table 9.3,the earliest start (ES)time for activity B is

(Multiple Choice)
4.8/5
(36)
A project's duration can be reduced by crashing activities on the critical path.
(True/False)
4.9/5
(35)
A project consists of the following activities:
Table 9.1
-Using Table 9.1,the amount of slack associated with activity C is

(Multiple Choice)
4.8/5
(37)
In general,projects are subject to less uncertainty than other types of processes.
(True/False)
4.9/5
(39)
The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,how much slack is associated with activity C?

(Multiple Choice)
4.9/5
(40)
A project consists of the following activities:
Table 9.1
-Using Table 9.1,the earliest start time for activity F is

(Multiple Choice)
4.8/5
(36)
The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the expected time to complete the project is

(Multiple Choice)
4.9/5
(27)
A project consists of the following activities:
Table 9.1
-Using Table 9.1,the latest start (LS)time for activity B is

(Multiple Choice)
4.8/5
(28)
A project consists of the following four activities with activity times in days:
Table 9.3
-Using Table 9.3,the earliest finish (EF)time for activity C is

(Multiple Choice)
4.7/5