A project consists of the following activities: A project consists of the following activities:    Table 9.1 -Using Table 9.1,the time complete the entire project is Table 9.1 -Using Table 9.1,the time complete the entire project is

Free
(Multiple Choice)
4.7/5
(31)
Correct Answer:
Verified

B

Because the critical path is the shortest path through a network it defines the minimum project completion time.

Free
(True/False)
4.8/5
(29)
Correct Answer:
Verified

False

PERT stands for program enterprise and resource technique.

Free
(True/False)
4.8/5
(21)
Correct Answer:
Verified

False

The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project. The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the earliest finish time for activity C is Table 9.2 -Using Table 9.2,the earliest finish time for activity C is

(Multiple Choice)
4.7/5
(35)

The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project. The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the variance of the project's total completion time is Table 9.2 -Using Table 9.2,the variance of the project's total completion time is

(Multiple Choice)
4.9/5
(33)

Which of the following is not a general characteristic of a project?

(Multiple Choice)
4.8/5
(49)

The slack time for an activity can be computed as

(Multiple Choice)
4.8/5
(38)

Global projects rarely are concerned with cultural differences among team members because English is the universal business language.

(True/False)
5.0/5
(41)

Indirect costs always increase as a project's duration decreases.

(True/False)
4.9/5
(28)

The earliest start time for an activity is at time zero.

(True/False)
4.7/5
(40)

A project consists of the following four activities with activity times in days: A project consists of the following four activities with activity times in days:     Table 9.3 -Using Table 9.3,the earliest start (ES)time for activity B is Table 9.3 -Using Table 9.3,the earliest start (ES)time for activity B is

(Multiple Choice)
4.8/5
(36)

A project's duration can be reduced by crashing activities on the critical path.

(True/False)
4.9/5
(35)

A project consists of the following activities: A project consists of the following activities:    Table 9.1 -Using Table 9.1,the amount of slack associated with activity C is Table 9.1 -Using Table 9.1,the amount of slack associated with activity C is

(Multiple Choice)
4.8/5
(37)

In general,projects are subject to less uncertainty than other types of processes.

(True/False)
4.9/5
(39)

The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project. The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,how much slack is associated with activity C? Table 9.2 -Using Table 9.2,how much slack is associated with activity C?

(Multiple Choice)
4.9/5
(40)

A project consists of the following activities: A project consists of the following activities:    Table 9.1 -Using Table 9.1,the earliest start time for activity F is Table 9.1 -Using Table 9.1,the earliest start time for activity F is

(Multiple Choice)
4.8/5
(36)

The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project. The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the expected time to complete the project is Table 9.2 -Using Table 9.2,the expected time to complete the project is

(Multiple Choice)
4.9/5
(27)

A project consists of the following activities: A project consists of the following activities:    Table 9.1 -Using Table 9.1,the latest start (LS)time for activity B is Table 9.1 -Using Table 9.1,the latest start (LS)time for activity B is

(Multiple Choice)
4.8/5
(28)

For activities on a project's critical path

(Multiple Choice)
4.8/5
(37)

A project consists of the following four activities with activity times in days: A project consists of the following four activities with activity times in days:     Table 9.3 -Using Table 9.3,the earliest finish (EF)time for activity C is Table 9.3 -Using Table 9.3,the earliest finish (EF)time for activity C is

(Multiple Choice)
4.7/5
(38)