Exam 17: Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The time required for a job to move through the system is referred to as flow time.

Free
(True/False)
4.8/5
(39)
Correct Answer:
Verified

True

If the following jobs are sequenced according to the SPT rule then the mean tardiness (in days)for all jobs is (assume zero for today's date) If the following jobs are sequenced according to the SPT rule then the mean tardiness (in days)for all jobs is (assume zero for today's date)

Free
(Multiple Choice)
4.9/5
(28)
Correct Answer:
Verified

C

If the following jobs are sequenced according to the DDATE rule then the maximum job tardiness (in days)is (assume zero for today's date) If the following jobs are sequenced according to the DDATE rule then the maximum job tardiness (in days)is (assume zero for today's date)

Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
Verified

C

The following set of jobs must be processed serially through a two-step system.The times at each process are in hours.If Johnson's Rule is used to sequence the jobs then Job C would start processing on operation 2 at The following set of jobs must be processed serially through a two-step system.The times at each process are in hours.If Johnson's Rule is used to sequence the jobs then Job C would start processing on operation 2 at

(Multiple Choice)
4.9/5
(31)

The process of prioritizing jobs that have been assigned to a resource is called sequencing.

(True/False)
4.8/5
(34)

Managers typically use multiple objective when constructing a schedule.

(True/False)
4.8/5
(38)

If the following jobs are sequenced according to the DDATE rule then job A would be completed on day (assume zero for today's date) If the following jobs are sequenced according to the DDATE rule then job A would be completed on day (assume zero for today's date)

(Multiple Choice)
4.9/5
(33)

If the following jobs are sequenced according to the DDATE rule then the mean completion time (in days)for all jobs is (assume zero for today's date) If the following jobs are sequenced according to the DDATE rule then the mean completion time (in days)for all jobs is (assume zero for today's date)

(Multiple Choice)
4.9/5
(36)

If the following jobs are sequenced according to the FCFS rule then the total number of jobs that would be late is (assume zero for today's date) If the following jobs are sequenced according to the FCFS rule then the total number of jobs that would be late is (assume zero for today's date)

(Multiple Choice)
4.9/5
(37)

If the following jobs are sequenced according to the SPT rule then the total number of jobs that would be late is (assume zero for today's date) If the following jobs are sequenced according to the SPT rule then the total number of jobs that would be late is (assume zero for today's date)

(Multiple Choice)
4.9/5
(35)

The scheduling rule that minimizes the makespan time for a set of jobs that must be processed through a two-step system where every job follows the same sequence through the two processes is

(Multiple Choice)
4.8/5
(31)

The following set of jobs must be processed serially through a two-step system.The times at each process are in hours.If Johnson's Rule is used to sequence the jobs then Job A would complete processing on operation 2 at The following set of jobs must be processed serially through a two-step system.The times at each process are in hours.If Johnson's Rule is used to sequence the jobs then Job A would complete processing on operation 2 at

(Multiple Choice)
4.9/5
(27)

The theory of constraints (TOC)approach to scheduling concentrates on scheduling the bottleneck resources.

(True/False)
4.8/5
(33)

Which of the following is not typically considered an objective of scheduling?

(Multiple Choice)
4.7/5
(34)

A ________ chart is used to show both planned and completed activities against a time scale.

(Multiple Choice)
4.9/5
(42)

Four products (1,2,3,and 4)must be processed on one of four machines (A,B,C,and D).The times required in minutes for each product on each machine are shown below. Four products (1,2,3,and 4)must be processed on one of four machines (A,B,C,and D).The times required in minutes for each product on each machine are shown below.   If management wishes to assign products to machines so that the total time to complete all the products is minimized,then Product 1 is assigned to If management wishes to assign products to machines so that the total time to complete all the products is minimized,then Product 1 is assigned to

(Multiple Choice)
4.7/5
(33)

Minimizing overtime is one of several objectives that could be considered when constructing a schedule.

(True/False)
4.8/5
(41)

If the following jobs are sequenced according to the FCFS rule then the mean tardiness (in days)for all jobs would be (assume zero for today's date) If the following jobs are sequenced according to the FCFS rule then the mean tardiness (in days)for all jobs would be (assume zero for today's date)

(Multiple Choice)
4.9/5
(36)

The dispatch list contains the order in which work is assigned to a productive resource.

(True/False)
4.8/5
(34)

Tardiness is defined as the difference between a job's flow time and makespan.

(True/False)
4.8/5
(31)
Showing 1 - 20 of 80
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)