Describe the Project Management Body of Knowledge PMBOK)area called Project Procurement Management.

Free
(Essay)
4.9/5
(35)
Correct Answer:
Verified

According to PMBOK,project procurement management is the contract management and change control processes required to administer contracts or purchase orders issued by authorized team members.It also includes the administration of any contract issued by an outside organization the buyer)that is acquiring the project from the performing organization the seller),and administering contractual obligations placed on the project team by the contract.

Describe how a fixed-price or lump-sum contract works.Give an example.

Free
(Essay)
4.8/5
(41)
Correct Answer:
Verified

A total or fixed price is negotiated or set as the final price for a specific product or service.They may include incentives for meeting certain objectives or penalties if those objectives are not met.Example: Payment of $1,000 to develop a Web site for an organization.

Which of the following is NOT a common outsourcing mistake?

Free
(Multiple Choice)
5.0/5
(38)
Correct Answer:
Verified

E

What is outsourcing? How does it related to Project Procurement Management?

(Essay)
5.0/5
(33)

Monitoring contract performance and making changes or taking corrective actions when needed refers to which of the following Project Procurement Management processes?

(Multiple Choice)
4.9/5
(34)

Why are personnel issues important when an organization or project manager is considering the outsourcing of activities?

(Essay)
4.9/5
(37)

Which of the following is NOT one of the Project Procurement Management processes outlined in the PMBOK Guide?

(Multiple Choice)
4.8/5
(34)

Performing due diligence to evaluate the financial strength of the vendor as a going concern helps protect against _____.

(Multiple Choice)
4.9/5
(38)

Organizations contemplating an outsourcing decision should keep things quiet until the last minute in order to shield its employees from undue stress.

(True/False)
4.9/5
(28)

Which of the following approaches provides flexibility to choose which project processes and deliverables should be from external sources and which should be internal to the organization?

(Multiple Choice)
4.8/5
(37)

Negotiating,selecting,and contracting with a seller for a particular product of service refers to which of the following Project Procurement Management processes?

(Multiple Choice)
4.9/5
(34)

Selective outsourcing provides flexibility to choose which project processes or deliverables should be outsourced and which should be kept internal.

(True/False)
4.7/5
(37)

A well-written contract should be precise,complete,balanced,and flexible.

(True/False)
4.7/5
(37)

Managing the relationship and contract between the buyer and seller is part of _____.

(Multiple Choice)
4.7/5
(36)

What is meant by full in-sourcing?

(Essay)
4.9/5
(42)

Not establishing an appropriate balance of power between the client and vendor is an example of the following common outsourcing mistake.

(Multiple Choice)
4.8/5
(33)

What is the purpose of a contract?

(Essay)
4.8/5
(41)

The decision whether to purchase or outsource specific project needs is similar to "make or buy" decision that compares the total direct and indirect costs of "making" a particular product or performing a particular service internally to the total direct and indirect costs of "buying" or contracting internally.

(True/False)
4.8/5
(36)

A large number of organizations have had negative experiences with outsourced projects and are now starting to bring projects back in-house.

(True/False)
4.8/5
(27)

A Web site developer negotiates a contract to develop a Web site for $2,000.This would be an example of a Fixed-Price/Lump-Sum contract

(True/False)
4.7/5
(42)