Changes in the scope boundary are handled through a _____.
A
Briefly describe the scope change control process.
Scope change control is concerned with ensuring that any changes to the project scope will be beneficial,with determining that an actual scope change has occurred,and with managing the actual changes when and as they occur.Scope control is also concerned with: Scope grope,Scope creep,and Scope lea
What is a deliverable definition table DDT)? What purpose does it serve?
All of the project deliverables must have a clear and concise definition.One way to communicate the project's deliverables is to create a deliverable definition table DDT).The purpose of the DDT is to:
-define all of the project-oriented deliverables
-define the structure of the deliverable.
-define the standards that provide a means to verify whether the deliverable was produced correctly
-name the person or position responsible for approving deliverables
-list the resources required for each deliverable
_____defines all project-oriented deliverables to be provided by the project team.
Joint application development is a group-based method where users and systems analysts jointly define the system requirements or design the system.
What is a deliverable structure chart DSC)? How does it map to a deliverable definition table DDT)?
Actors are people or external systems that are elements of a data flow diagram DFD).
What is a work breakdown structure WBS)? How does it map to the DDT and DSC?
Project scope is a statement detailing the features and functions that must support the IT solution.
One way to communicate the project's deliverables is to create a deliverable definition table.
Scope change control procedures protect the scope boundary from expanding as a result of increasing featurism.
The development of a work breakdown structure is an interim step to define detailed work packages used to estimate the project schedule and budget.
The scope boundary establishes only those elements that are a part of the project work to be completed by the project team.
Which of the following processes of Scope Management Process defines what work will and will not be included in the project?
Scope verification confirms that the scope is complete and accurate.