Exam 14: Project Implementation, closure, and Evaluation
Exam 1: The Nature of Information Technology Projects56 Questions
Exam 2: Initializing and Conceptualizing the IT Project63 Questions
Exam 3: The Project Infrastructure61 Questions
Exam 4: The Human Side of Project Management53 Questions
Exam 5: Defining and Managing Project and Product Scope49 Questions
Exam 6: The Work Breakdown Structure and Project Estimation66 Questions
Exam 7: The Project Schedule and Budget64 Questions
Exam 8: Managing Project Risk69 Questions
Exam 9: Project Communication,tracking,and Reporting63 Questions
Exam 10: It Project Quality Management71 Questions
Exam 11: Managing Organizational Change, resistance, and Conflict81 Questions
Exam 12: Project Procurement Management and Outsourcing73 Questions
Exam 13: Leadership and Ethics75 Questions
Exam 14: Project Implementation, closure, and Evaluation65 Questions
Select questions type
Assessment of the project manager and project team occurs during the _____ .
Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
C
Demonstrating that all project deliverables have been completed occurs during _____.
Free
(Multiple Choice)
4.9/5
(40)
Correct Answer:
E
Delivery,installation,and implementation of the information system indicate the sponsor's acceptance of the project.
Free
(True/False)
4.8/5
(39)
Correct Answer:
False
What is a perpetual project? Why might an organization be reluctant to terminate a project that many would consider unsuccessful?
(Essay)
4.9/5
(38)
The project MOV is usually readily determined at the close of the project.
(True/False)
4.9/5
(31)
The project audit is the generally conducted by the project manager and project team.
(True/False)
4.9/5
(45)
What are the advantages and disadvantages of the direct cutover approach?
(Essay)
4.8/5
(38)
The final project report may be circulated to key stakeholders prior to the final meeting and presentation.
(True/False)
4.9/5
(43)
Failure to clearly define and agree on the project's MOV may lead to a runaway or perpetual project.
(True/False)
4.9/5
(40)
The formal exchange of the project's product from the project team to the organization occurs during _____ .
(Multiple Choice)
4.8/5
(32)
Which implemention approach is usually the most expensive and least risky?
(Multiple Choice)
4.8/5
(34)
_____ is the least favored implementation approach due to the higher level of risk.
(Multiple Choice)
4.8/5
(37)
Having the team review the project scope,schedule,budget,and quality objectives would most likely occur in the:
(Multiple Choice)
4.8/5
(39)
The parallel implementation approach is generally considered to be the riskiest implementation approach.
(True/False)
4.9/5
(36)
With _____,users may have to enter data into multiple systems to compare the outputs.
(Multiple Choice)
4.9/5
(26)
Immediately after the implementation,the project's MOV can be determined.
(True/False)