Exam 14: Project Planning and Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The purpose of performing a forward pass is to:

Free
(Multiple Choice)
4.9/5
(31)
Correct Answer:
Verified

B

PERT assumes that the statistical variation in total project completion times can be computed by adding the standard deviations along the critical path.

Free
(True/False)
4.9/5
(33)
Correct Answer:
Verified

False

Project management requires:

Free
(Multiple Choice)
4.8/5
(26)
Correct Answer:
Verified

D

The project management concept that can be best applied to situations such as R&D,computer systems design,and military invasions is:

(Multiple Choice)
4.9/5
(28)

Gantt charts are effective if:

(Multiple Choice)
4.8/5
(31)

The job of the project manager is to:

(Multiple Choice)
4.7/5
(33)

CPM network scheduling assumes a second order (non-linear)time-cost tradeoff exists.

(True/False)
4.9/5
(33)

The advantage(s)of the network method over the Gantt chart is (are)that:

(Multiple Choice)
4.8/5
(37)

An assumption of PERT is:

(Multiple Choice)
4.8/5
(36)

The advantage(s)that Gantt chart has over the network method is (are):

(Multiple Choice)
4.8/5
(29)

Which of the following statements about CPM is true?

(Multiple Choice)
4.8/5
(29)

"Slack" refers to the difference between:

(Multiple Choice)
4.7/5
(31)

Controlling a project does NOT entail:

(Multiple Choice)
4.9/5
(44)

A forward pass of the above network indicates that the early start time of activity 4-5 is:

(Multiple Choice)
4.8/5
(30)

Estimating the time required for each task is an example of a ______ management decision in project management.

(Multiple Choice)
4.9/5
(33)

Which of the following statements is incorrect about the PERT method of project scheduling?

(Multiple Choice)
4.9/5
(43)

Which of the following statements is true about a critical path?

(Multiple Choice)
4.8/5
(35)

A work-breakdown structure is used in the scheduling activity of project management.

(True/False)
4.9/5
(32)

A network-based project scheduling method that requires three time estimates for each activity is:

(Multiple Choice)
4.9/5
(29)

A forward pass is required while computing the early start and early finish times of activities.

(True/False)
4.8/5
(38)
Showing 1 - 20 of 22