Exam 14: Project Planning and Scheduling
Exam 1: The Operations Function25 Questions
Exam 2: Operations and Supply Chain Strategy26 Questions
Exam 3: Product Design27 Questions
Exam 4: Process Selection35 Questions
Exam 5: Service Process Design30 Questions
Exam 6: Process-Flow Analysis27 Questions
Exam 7: Lean Thinking and Lean Systems33 Questions
Exam 8: Managing Quality31 Questions
Exam 9: Quality Control and Improvement36 Questions
Exam 10: Supply Chain Management29 Questions
Exam 11: Forecasting31 Questions
Exam 12: Capacity Planning23 Questions
Exam 13: Scheduling Operations23 Questions
Exam 14: Project Planning and Scheduling22 Questions
Exam 15: Independent Demand Inventory30 Questions
Exam 16: Materials Requirements Planning and ERP30 Questions
Select questions type
The purpose of performing a forward pass is to:
Free
(Multiple Choice)
4.9/5
(31)
Correct Answer:
B
PERT assumes that the statistical variation in total project completion times can be computed by adding the standard deviations along the critical path.
Free
(True/False)
4.9/5
(33)
Correct Answer:
False
The project management concept that can be best applied to situations such as R&D,computer systems design,and military invasions is:
(Multiple Choice)
4.9/5
(28)
CPM network scheduling assumes a second order (non-linear)time-cost tradeoff exists.
(True/False)
4.9/5
(33)
The advantage(s)of the network method over the Gantt chart is (are)that:
(Multiple Choice)
4.8/5
(37)
The advantage(s)that Gantt chart has over the network method is (are):
(Multiple Choice)
4.8/5
(29)
A forward pass of the above network indicates that the early start time of activity 4-5 is:
(Multiple Choice)
4.8/5
(30)
Estimating the time required for each task is an example of a ______ management decision in project management.
(Multiple Choice)
4.9/5
(33)
Which of the following statements is incorrect about the PERT method of project scheduling?
(Multiple Choice)
4.9/5
(43)
Which of the following statements is true about a critical path?
(Multiple Choice)
4.8/5
(35)
A work-breakdown structure is used in the scheduling activity of project management.
(True/False)
4.9/5
(32)
A network-based project scheduling method that requires three time estimates for each activity is:
(Multiple Choice)
4.9/5
(29)
A forward pass is required while computing the early start and early finish times of activities.
(True/False)
4.8/5
(38)
Showing 1 - 20 of 22