Exam 26: Learning Curves
Exam 1: Operations and Productivity127 Questions
Exam 2: The Global Environment and Operations Strategy119 Questions
Exam 3: Managing Projects120 Questions
Exam 4: Forecasting Demand140 Questions
Exam 5: Product Design118 Questions
Exam 6: Quality Management and International Standards123 Questions
Exam 7: Process Design108 Questions
Exam 8: Location Decisions121 Questions
Exam 9: Layout Decisions146 Questions
Exam 10: Job Design and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Managing Inventory163 Questions
Exam 13: Aggregate Scheduling116 Questions
Exam 14: Material Requirements Planning Mrpand Erp113 Questions
Exam 15: Scheduling for the Short-Term116 Questions
Exam 16: Jit,lean Operations,and the Toyota Production System115 Questions
Exam 17: Maintenance and Reliability Decisions111 Questions
Exam 18: Sustainability80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity Planning96 Questions
Exam 21: Supply Chain Modeling55 Questions
Exam 22: Decision Modeling97 Questions
Exam 23: Linear Programming Models88 Questions
Exam 24: Transportation Modeling89 Questions
Exam 25: Queuing Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Modeling with Simulation75 Questions
Select questions type
Which of the following is a limitation of the use of learning curves?
(Multiple Choice)
4.7/5
(35)
Explain how learning curves might be applied in a bid preparation application.
(Essay)
4.8/5
(35)
Which one of the following statements about learning curves is TRUE?
(Multiple Choice)
4.9/5
(46)
In addition to labor,to which other variables have learning curves been applied?
(Essay)
4.8/5
(29)
Describe the earliest application of learning curve concepts to industry.
(Essay)
4.9/5
(41)
A certain product under development took 200 hours for the production of its 2nd unit and 180 hours for its 4th unit.
a.What is the learning curve?
b.How much time did the first unit take?
c.How much time would the production of the 10th unit take? (Use both the formula and the Table E.3 approach.Do the two versions agree?)
(Essay)
4.7/5
(27)
Which one of the following courses of actions would NOT be taken by a firm wanting to pursue a learning curve steeper than the industry average?
(Multiple Choice)
4.8/5
(34)
Explain how learning curves might be applied in a scheduling application.
(Essay)
4.9/5
(32)
The earliest industrial application of learning curves came from a report by ________.
(Essay)
4.8/5
(36)
The learning-curve table approach may be simpler to use than the formula approach,but it requires the presence of a table of learning-curve coefficients.
(True/False)
4.9/5
(31)