Exam 1: An Overview of the Building Delivery Process How Buildings Come Into Being
Exam 1: An Overview of the Building Delivery Process How Buildings Come Into Being80 Questions
Exam 2: Design and Constructions Regulations75 Questions
Exam 3: Loads on Buildings77 Questions
Exam 4: Load Resistance the Structural Properties of Materials74 Questions
Exam 5: Properties of the Envelope-I Thermal Properties102 Questions
Exam 6: Properties of the Envelope-II Air and Water Vapor Control75 Questions
Exam 7: Fire and Smoke-Related Properties84 Questions
Exam 8: Acoustical Properties of Materials41 Questions
Exam 9: Principles of Joints and Sealants Expansion and Contraction Control54 Questions
Exam 10: Principles of Sustainable Construction71 Questions
Exam 11: Soils and Excavations68 Questions
Exam 12: Below-Grade Construction Foundation Systems and Basements55 Questions
Exam 13: Materials for Wood Construction-I Lumber89 Questions
Exam 14: Materials for Wood Construction-Ii Engineered Wood Products, Fasteners, and Connectors71 Questions
Exam 15: Wood Light-Frame Construction-I75 Questions
Exam 16: Wood Light-Frame Construction-II54 Questions
Exam 17: Structural Insulated Panel Construction24 Questions
Exam 18: Material Steel and Steel Components86 Questions
Exam 19: Structural Steel Construction55 Questions
Exam 20: Cold-Formed Steel Construction81 Questions
Exam 21: Lime, Portland Cement, and Concrete99 Questions
Exam 22: Concrete Construction-I Formwork, Reinforcement, and Slabs-On-Ground84 Questions
Exam 23: Concrete Construction-II Site-Cast and Precast Concrete Framing Systems60 Questions
Exam 24: Masonry Materials-I Mortar and Brick83 Questions
Exam 25: Masonry Materials-II Concrete Masonry Units, Natural Stone, and Glass Masonry Units76 Questions
Exam 26: Masonry and Concrete Bearing Wall Construction81 Questions
Exam 27: Exterior Wall Cladding-I Principles of Rainwater Infiltration Control42 Questions
Exam 28: Exterior Wall Cladding-II Masonry, Precast Concrete, and Gfrc98 Questions
Exam 29: Exterior Wall Cladding-III Stucco, Adhered Veneer, Eifs, Natural Stone, and Insulated Metal Panels89 Questions
Exam 30: Glass, Glazing, and Light-Transmitting Plastics94 Questions
Exam 31: Windows and Doors46 Questions
Exam 32: Exterior Wall Cladding-Iv Wall System in Glass49 Questions
Exam 33: Roofing-I Low-Slope Roofs107 Questions
Exam 34: Roofing-I Steep Roofs55 Questions
Exam 35: Stairs40 Questions
Exam 36: Floor Coverings53 Questions
Exam 37: Ceilings23 Questions
Select questions type
Of the various project delivery methods described in the text, the oldest method is
(Multiple Choice)
4.8/5
(31)
How do GCs generally obtain information on upcoming construction projects that they could bid for?
(Essay)
4.7/5
(35)
The certificate of occupancy predates substantial completion inspection of the project.
(True/False)
4.9/5
(40)
Who is responsible for ensuring the safety of workers on the construction site of a typical building project?
(Multiple Choice)
4.8/5
(38)
In a typical building project, the GC must provide (and pay for)all three surety bonds-bid bond, performance bond, and payment bond-to the owner. In certain situations, the owner may waive bid bond requirement. Mention one such situation.
(Essay)
5.0/5
(23)
The design phase of a project is generally divided into three stages that are sequential. List these stages in sequential order in spelt- out format along with their acronyms.
(Essay)
5.0/5
(39)
The owner is required to provide payment bond to the GC whose bid has been accepted
(Multiple Choice)
4.8/5
(43)
Explain the purposes of the three surety bonds used in a typical building project, and the stages at which they are provided.
(Essay)
4.8/5
(30)
The construction drawings of a building project are prepared during the
(Multiple Choice)
4.7/5
(34)
List the important items contained in a project manual. At what stage are addenda and contract modifications added to the document that will finally become the project manual?
(Essay)
4.8/5
(35)
Shop drawings are prepared during the design phase of the project.
(True/False)
4.8/5
(39)
The project delivery method that should ensure the least amount of litigation among parties contributing to the project is the
(Multiple Choice)
4.8/5
(31)
The primary purpose of the contract modification procedure in the agreement between the owner and the GC is to allow change orders.
(True/False)
5.0/5
(35)
Establishing the project's economic feasibility and its overall budget is part of the design phase of the project.
(True/False)
4.9/5
(34)
Showing 61 - 80 of 80
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)