Exam 6: Developing a Project Schedule
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
A _________ activity is one that has more than one activity immediately following it.
(Multiple Choice)
4.8/5
(41)
________ activities must be completed immediately before a particular activity.
(Multiple Choice)
4.8/5
(35)
If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a
(Multiple Choice)
4.8/5
(34)
Determine the critical path, total slacks for each activity and project duration for the network represented by the following table. Discuss the degree of sensitivity embodied by the network.
(Essay)
4.8/5
(30)
A sequence of connected, dependent activities is termed a(n)
(Multiple Choice)
4.9/5
(27)
A merge activity is one that merges with other activities into a succeeding activity.
(True/False)
4.9/5
(34)
Consider the following table of activities A through G in which A is the start node and G is the stop node.
(Multiple Choice)
4.9/5
(35)
Arrows on an activity-on-node (AON) project network represent
(Multiple Choice)
4.8/5
(28)
If a network has more than one critical path but noncritical activities have very little slack, the network is considered to have a high level of sensitivity.
(True/False)
4.7/5
(35)
Consider the following table of activities A through G in which A is the start node and G is the stop node.
(Multiple Choice)
4.9/5
(40)
________ slack must be coordinated with all participants in the activities that follow in the chain.
(Multiple Choice)
4.8/5
(42)
It is possible for a project network to have more than one critical path.
(True/False)
4.7/5
(32)
Briefly describe looping and conditional statements and explain why they are not allowed when developing project networks.
(Essay)
4.9/5
(32)
In the network computation process what is a forward pass and what three things does it determine?
(Essay)
4.8/5
(28)
The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.
(Multiple Choice)
4.7/5
(31)
Different activities along the same path can have different total slack.
(True/False)
5.0/5
(35)
One piece of information that the arrows within the Activity-on-Node network can convey is
(Multiple Choice)
4.7/5
(23)