Exam 6: Developing a Project Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

___________ reflects the likelihood the original critical path(s) will change once the project is initiated.

(Multiple Choice)
4.9/5
(32)

An activity has a duration of 10 days. Its early start is 5 and its late start is 8. This activity has _____ days of total slack.

(Multiple Choice)
4.8/5
(39)

In the network computation process what is a backward pass and what four things does it determine?

(Essay)
4.8/5
(37)

A(n) __________ activity is frequently used to identify the use of fixed resources or costs over a segment of the project.

(Multiple Choice)
4.8/5
(27)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

(Multiple Choice)
4.8/5
(35)

After the total slack for each activity is identified, the project manager can more easily identify the

(Multiple Choice)
4.8/5
(36)

A project manager is building a project network that involves testing a prototype. She must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, she must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of

(Multiple Choice)
4.9/5
(36)

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as

(Multiple Choice)
4.8/5
(38)

It is acceptable for arrows to cross one another in a network diagram.

(True/False)
4.9/5
(38)

If the project has a duration of 8 days, the project should be completed 8 days from the day it starts.

(True/False)
4.8/5
(35)

The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project.

(True/False)
4.9/5
(37)

The amount of delay within a task that will not delay the overall project is known as a

(Multiple Choice)
4.8/5
(29)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

(Multiple Choice)
5.0/5
(40)

The WBS identifies dependencies, the sequencing of activities, and the timing of activities.

(True/False)
4.8/5
(39)

Identify the four types of lags giving an example for each type.

(Short Answer)
4.8/5
(42)

Which of the following represents an activity on an activity-on-node (AON) project network?

(Multiple Choice)
4.8/5
(28)

An activity is an element of the project that always requires time.

(True/False)
4.8/5
(40)

An element in the project that consumes time is a(n) ___________.

(Multiple Choice)
4.8/5
(34)

An activity cannot begin until ALL preceding connected activities have been completed.

(True/False)
4.7/5
(31)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

(Multiple Choice)
4.8/5
(33)
Showing 21 - 40 of 128
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)