Exam 6: Developing a Project Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Gantt charts are popular because they represent an easy-to-understand, clear picture on a time-scaled horizon.

(True/False)
4.8/5
(29)

When translated into a project network, a work package will become

(Multiple Choice)
4.8/5
(32)

When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities.

(True/False)
4.9/5
(31)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

(Multiple Choice)
4.9/5
(35)

Only activities that occur at the end of a chain of activities can have free slack.

(True/False)
4.8/5
(37)

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?

(Multiple Choice)
4.8/5
(36)

An activity that has more than one dependency arrow flowing into it is termed a(n)

(Multiple Choice)
4.8/5
(34)

________ activities are to be completed immediately following a particular activity.

(Multiple Choice)
4.9/5
(36)

The longest path through a project network is called the _________.

(Multiple Choice)
4.7/5
(40)

When completing the forward pass, the project duration is determined. A project duration of 45 days doesn't mean that if the project were to start today it would be complete in 45 days. Explain.

(Essay)
4.9/5
(38)

What is a Gantt chart and what advantages does it have over project networks?

(Essay)
4.7/5
(38)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

(Multiple Choice)
4.9/5
(33)

Which of the following is true about hammock activities?

(Multiple Choice)
4.8/5
(36)

In developing a project network, neither looping nor conditional statements are permitted.

(True/False)
4.8/5
(29)

Which of the following correctly calculates the late start for an activity?

(Multiple Choice)
4.8/5
(41)

When completing a forward pass, you carry the early finish to the next activity where it becomes its early start, unless the next succeeding activity is a merge activity. In this case you select the largest early finish number of all its immediate predecessor activities. Why do you select the largest early finish number?

(Essay)
4.8/5
(28)

When an activity with a long duration is broken into smaller segments so that the following activities can begin sooner it is called __________.

(Multiple Choice)
4.9/5
(30)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

(Multiple Choice)
4.8/5
(43)

Which of the following will correctly calculate the total slack in an activity?

(Multiple Choice)
4.8/5
(41)

What is a lag and give an example of when you would need to use one?

(Essay)
4.8/5
(30)
Showing 101 - 120 of 128
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)