Exam 6: Developing a Project Schedule
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
Gantt charts are popular because they represent an easy-to-understand, clear picture on a time-scaled horizon.
(True/False)
4.8/5
(29)
When translated into a project network, a work package will become
(Multiple Choice)
4.8/5
(32)
When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities.
(True/False)
4.9/5
(31)
Consider the following table of activities A through G in which A is the start node and G is the stop node.
(Multiple Choice)
4.9/5
(35)
Only activities that occur at the end of a chain of activities can have free slack.
(True/False)
4.8/5
(37)
The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?
(Multiple Choice)
4.8/5
(36)
An activity that has more than one dependency arrow flowing into it is termed a(n)
(Multiple Choice)
4.8/5
(34)
________ activities are to be completed immediately following a particular activity.
(Multiple Choice)
4.9/5
(36)
The longest path through a project network is called the _________.
(Multiple Choice)
4.7/5
(40)
When completing the forward pass, the project duration is determined. A project duration of 45 days doesn't mean that if the project were to start today it would be complete in 45 days. Explain.
(Essay)
4.9/5
(38)
What is a Gantt chart and what advantages does it have over project networks?
(Essay)
4.7/5
(38)
Consider the following table of activities A through G in which A is the start node and G is the stop node.
(Multiple Choice)
4.9/5
(33)
In developing a project network, neither looping nor conditional statements are permitted.
(True/False)
4.8/5
(29)
Which of the following correctly calculates the late start for an activity?
(Multiple Choice)
4.8/5
(41)
When completing a forward pass, you carry the early finish to the next activity where it becomes its early start, unless the next succeeding activity is a merge activity. In this case you select the largest early finish number of all its immediate predecessor activities. Why do you select the largest early finish number?
(Essay)
4.8/5
(28)
When an activity with a long duration is broken into smaller segments so that the following activities can begin sooner it is called __________.
(Multiple Choice)
4.9/5
(30)
Consider the following table of activities A through G in which A is the start node and G is the stop node.
(Multiple Choice)
4.8/5
(43)
Which of the following will correctly calculate the total slack in an activity?
(Multiple Choice)
4.8/5
(41)
What is a lag and give an example of when you would need to use one?
(Essay)
4.8/5
(30)
Showing 101 - 120 of 128