Exam 6: Developing a Project Schedule
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
On a project network, the activity times are derived from the
(Multiple Choice)
5.0/5
(39)
A(n) _____________ calculates how late an activity can start and finish.
(Multiple Choice)
4.8/5
(25)
When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
(Multiple Choice)
4.9/5
(38)
On a piece of scratch paper, draw an early-start Gantt Chart for the following table. What does a Gantt Chart tell you that a network chart does not?
(Essay)
4.8/5
(35)
In a project network, ________ indicate activity dependency and project flow.
(Multiple Choice)
4.7/5
(44)
Which of the following can be used without coordinating with managers of succeeding activities?
(Multiple Choice)
4.9/5
(29)
Which of the following is provided by both the project network and the work breakdown structure?
(Multiple Choice)
4.8/5
(31)
Consider the following table of activities A through G in which A is the start node and G is the stop node.
(Multiple Choice)
4.8/5
(39)
Consider the following table of activities A through G in which A is the start node and G is the stop node.
(Multiple Choice)
4.8/5
(46)
Which of the following correctly calculates the early finish for an activity?
(Multiple Choice)
4.9/5
(32)
Experience suggests that when there are multiple starts, a common start node should be used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending.
(True/False)
4.9/5
(44)
Using free slack does not delay any following activities and requires no coordination with managers of other activities.
(True/False)
4.9/5
(34)
Activities that must occur immediately before a given activity are called ________ activities.
(Multiple Choice)
4.8/5
(26)
The assumption that all immediately preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called
(Multiple Choice)
4.9/5
(34)
Activities that can occur while another activity is taking place are called ________ activities.
(Multiple Choice)
4.8/5
(39)
When creating a project network, your primary input source will be the
(Multiple Choice)
4.9/5
(34)
In a project network, recycling through a set of activities or __________ is not permitted.
(Multiple Choice)
4.9/5
(32)
Consider the following table of activities A through G in which A is the start node and G is the stop node.
(Multiple Choice)
4.8/5
(32)
Showing 81 - 100 of 128
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)