Exam 6: The Work Breakdown Structure and Project Estimation
Exam 1: The Nature of Information Technology Projects51 Questions
Exam 2: Project Methodologies and Processes66 Questions
Exam 3: Measurable Organizational Value and the Business Case50 Questions
Exam 4: Project Planning: the Project Infrastructure72 Questions
Exam 5: Project Planning: Scope and the Work Breakdown Structure94 Questions
Exam 6: The Work Breakdown Structure and Project Estimation84 Questions
Exam 7: Managing Project Risk77 Questions
Exam 8: Managing Project Stakeholders and Communication66 Questions
Exam 9: Managing Project Quality60 Questions
Exam 10: Leading the Project Team90 Questions
Exam 11: Managing Organizational Change, Resistance, and Conflict92 Questions
Exam 12: Project Completion79 Questions
Select questions type
Installing a server before loading the operating system is an example of a finish-to-start relationship.
(True/False)
4.8/5
(28)
PERT was developed in the 1950s to create a visual representation of scheduled activities, their logical sequence, and interrelationships using a statistical probability distribution.
(True/False)
4.8/5
(34)
_____is ensuring that project resources are not overallocated.
(Multiple Choice)
4.9/5
(39)
Time and effort needed to gather experience on a technology or process are _____
(Multiple Choice)
4.7/5
(36)
Under the Precedence Diagramming Method, the situation which occurs when two activities can start at different times, have different durations, but are planned to be competed at the same time is called:
(Multiple Choice)
4.8/5
(40)
Construct an Activity on the Node (AON) network diagram with at least 5 tasks that illustrate predecessors, successors and parallel activities.Label the nodes appropriately and assuming your tasks show estimated durations in days, state the estimated time for completing your project.
(Essay)
4.9/5
(30)
The idea that there is a cost associated with using a resource is _____
(Multiple Choice)
4.9/5
(36)
Under the Precedence Diagramming Method, the most common relationship between two activities which implies a logical sequence is called:
(Multiple Choice)
4.8/5
(32)
A parallel activity is a task that can be worked on at the same time as another activity.
(True/False)
4.9/5
(30)
Predecessor activities are activities that can be worked on at the same time as another activity.
(True/False)
4.9/5
(34)
The technique used to help manage the Polaris submarine project and which bases activity estimates on probabilistic estimates of three scenarios is most closely associated with:
(Multiple Choice)
4.7/5
(25)
In the context of critical chain project management, what is resource contention?
(Essay)
4.9/5
(35)
How can parallel activities help shorten the project schedule? Are there any trade-offs?
(Essay)
4.7/5
(36)
The tool most closely associated with activity bars across a horizontal time axis is:
(Multiple Choice)
4.8/5
(38)
What is the difference between crashing and fast tracking a project's schedule?
(Essay)
4.9/5
(36)
The project budget is determined by the project schedule, the cost of the resources assigned to each of the tasks, and by any other direct or indirect costs and reserves.
(True/False)
4.9/5
(33)
Once the project schedule and project budget are approved they become the _____
(Multiple Choice)
4.9/5
(33)
_____ is well suited for developing simulations where the project manager can conduct sensitivity analysis for schedule planning and risk analysis.
(Multiple Choice)
4.8/5
(38)
Showing 21 - 40 of 84
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)