Exam 7: B: Design of Work Systems
Exam 1: Introduction to Operations Management63 Questions
Exam 2: Competitiveness, Strategic Planning, and Productivity54 Questions
Exam 3: Demand Forecasting172 Questions
Exam 4: A: Product Design74 Questions
Exam 4: B: Product Design56 Questions
Exam 5: A: Strategic Capacity Planning74 Questions
Exam 5: B: Strategic Capacity Planning64 Questions
Exam 6: A: Process Design and Facility Layout157 Questions
Exam 6: B: Process Design and Facility Layout99 Questions
Exam 7: A: Design of Work Systems143 Questions
Exam 7: B: Design of Work Systems68 Questions
Exam 8: A: Location Planning and Analysis74 Questions
Exam 8: B: Location Planning and Analysis16 Questions
Exam 9: Management of Quality98 Questions
Exam 10: A: Statistical Quality Control121 Questions
Exam 10: B: Statistical Quality Control61 Questions
Exam 11: Supply Chain Management86 Questions
Exam 12: Inventory Management168 Questions
Exam 13: Aggregate Operations Planning71 Questions
Exam 14: Material Requirements Planning and Enterprise Resource Planning84 Questions
Exam 15: A: Just-In-Time and Lean Production82 Questions
Exam 15: B: Just-In-Time and Lean Production32 Questions
Exam 16: Job and Staff Scheduling112 Questions
Exam 17: Project Management127 Questions
Exam 18: A: Waiting-Line Analysis76 Questions
Exam 18: B: Waiting-Line Analysis41 Questions
Select questions type
Unit times for a job exhibit a learning effect.If the 2nd unit took 30 hours,and the 4th unit took 21 hours,roughly how many hours would you estimate the 3rd unit took?
(Multiple Choice)
4.8/5
(35)
Which one of the following would learning curves probably affect the least?
(Multiple Choice)
4.9/5
(35)
Developing work assignments in a job shop in a certain firm has a learning curve of 80 percent.If the second set of assignments takes 12 minutes,determine the length of time required for the following:
(i)the fifth set
(ii)sets 3,4,and 5 together
(Essay)
4.8/5
(38)
A company is preparing a bid on a government contract for 40 units of a certain product.The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours,respectively.Approximately how long will it take to produce the 15th unit?
(Multiple Choice)
4.8/5
(35)
A job is expected to have a learning curve of 90 percent.The third unit required 16 hours.The twelfth unit should take approximately how many hours?
(Multiple Choice)
4.7/5
(33)
A 98% learning curve implies an exceptionally rapid rate of improvement.
(True/False)
4.8/5
(38)
It took exactly 10 hours to produce the first widget on a 100 percent learning curve.The second widget will take how many hours to produce?
(Multiple Choice)
4.7/5
(37)
A manager wants to analyze the learning curve associated with producing one of his company's products.Accordingly,he has gathered the following data:
Approximately how long will it take to produce the fifth through tenth units?

(Multiple Choice)
4.8/5
(41)
A company is preparing a bid on a government contract for 40 units of a certain product.The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours,respectively.If the contract is cancelled after the first 20 units,approximately how much of the expected total direct labour will have been expended to that point?
(Multiple Choice)
4.7/5
(36)
A learning rate of 97% will produce minor decreases in completion times of the first few units.
(True/False)
4.9/5
(45)
An 80 percent learning curve means that with each doubling of units there will be a 20 percent decrease in time per unit.
(True/False)
4.8/5
(39)
A 77% learning curve will produce relatively minor decreases in completion times of the first few repetitions.
(True/False)
4.8/5
(43)
Learning curves have little relevance for planning or scheduling of routine activities of short duration.
(True/False)
4.9/5
(32)
According to learning curve theory,for certain kinds of tasks the indirect labour time or cost per unit decreases as the number of units increases.
(True/False)
4.9/5
(40)
Learning curves cannot be used if the labour time for the first unit is unknown.
(True/False)
4.8/5
(29)
Learning curves are used primarily for mass production applications.
(True/False)
4.8/5
(37)
A manager is trying to estimate the learning rate for a new job.The first unit took 16 hours,and the fourth unit required about 13 hours.The learning rate is:
(Multiple Choice)
4.8/5
(25)
A manager wants to analyze the learning curve associated with producing one of his company's products.Accordingly,he has gathered the following data:
Approximately how long will it take to produce the tenth unit?

(Multiple Choice)
4.8/5
(27)
In which of the following managerial activities would learning curves probably be the least useful?
(Multiple Choice)
4.7/5
(33)
Showing 21 - 40 of 68
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)